Indkøb: Bygge- og anlægsarbejde i forbindelse med kraftværker, mineanlæg og fremstillingsvirksomheder samt bygninger i tilknytning til olie- og gasindustrien (side 6)
2015-12-22Contract B12 — secondary buildings and constructions (HOFOR Energiproduktion A/S)
HOFOR, Hovedstadsområdets Forsyningsselskab, is building a new biomass fueled power plant at the existing Amager Power Plant with a performance of 500 MWh. The entire project for the building complex, the storage facilities and the conveyor system is called BIO4. The building complex consists of turbine- and electrical building, boiler building and flue gas treatment building. It is approximately 50 meters wide and 205 meters long. The highest point of the building is approximately 70 meters above ground …
Se udbuddet »
2015-12-22Contract B6 — steel structures, building complex (HOFOR Energiproduktion A/S)
HOFOR, Hovedstadsområdets Forsyningsselskab, is building a new biomass fueled power plant at the existing Amager Power Plant with a performance of 500 MWh. The entire project for the building complex, the storage facilities and the conveyor system is called BIO4. The building complex consists of turbine- and electrical building, boiler building and flue gas treatment building. It is approximately 50 meters wide and 205 meters long. The highest point of the building is approximately 70 meters above ground …
Se udbuddet » Nævnte leverandører:MT Højgaard
2015-12-22Contract B5 — concrete constructions, storage buildings (HOFOR Energiproduktion A/S)
HOFOR, Hovedstadsområdets Forsyningsselskab, is building a new biomass fueled power plant at the existing Amager Power Plant with a performance of 500 MWh. The entire project for the building complex, the storage facilities and the conveyor system is called BIO4. The building complex consists of turbine- and electrical building, boiler building and flue gas treatment building. It is approximately 50 meters wide and 205 meters long. The highest point of the building is approximately 70 meters above ground …
Se udbuddet » Nævnte leverandører:Arkil A/S
2015-12-22Contract B3 — concrete constructions, transportation facilities and harbor (HOFOR Energiproduktion A/S)
HOFOR, Hovedstadsområdets Forsyningsselskab, is building a new biomass fueled power plant at the existing Amager Power Plant with a performance of 500 MWh. The entire project for the building complex, the storage facilities and the conveyor system is called BIO4. The building complex consists of turbine- and electrical building, boiler building and flue gas treatment building. It is approximately 50 meters wide and 205 meters long. The highest point of the building is approximately 70 meters above ground …
Se udbuddet » Nævnte leverandører:Züblin A/S
2015-12-22Contract B2 — piling (HOFOR Energiproduktion A/S)
HOFOR, Hovedstadsområdets Forsyningsselskab, is building a new biomass fueled power plant at the existing Amager Power Plant with a performance of 500 MWh. The entire project for the building complex, the storage facilities and the conveyor system is called BIO4. The building complex consists of turbine- and electrical building, boiler building and flue gas treatment building. It is approximately 50 meters wide and 205 meters long. The highest point of the building is approximately 70 meters above ground …
Se udbuddet » Nævnte leverandører:Per Aarsleff A/S
2015-12-22Contract B4 — concrete constructions, building complex (HOFOR Energiproduktion A/S)
HOFOR, Hovedstadsområdets Forsyningsselskab, is building a new biomass fueled power plant at the existing Amager Power Plant with a performance of 500 MWh. The entire project for the building complex, the storage facilities and the conveyor system is called BIO4. The building complex consists of turbine- and electrical building, boiler building and flue gas treatment building. It is approximately 50 meters wide and 205 meters long. The highest point of the building is approximately 70 meters above ground …
Se udbuddet » Nævnte leverandører:Per Aarsleff A/S
2015-12-22Contract B1 — construction site (HOFOR Energiproduktion A/S)
HOFOR, Hovedstadsområdets Forsyningsselskab, is building a new biomass fuelled power plant at the existing Amager Power Plant with a performance of 500 MWh. The entire project for the building complex, the storage facilities and the conveyor system is called BIO4. The building complex consists of turbine — and electrical building, boiler building and flue gas treatment building. It is approximately 50 meters wide and 205 meters long. The highest point of the building is approximately 70 meters above …
Se udbuddet » Nævnte leverandører:NCC Danmark A/S
2015-12-22Rammeaftale om løbende vedligehold af konstruktioner på A/S Øresunds landanlæg (A/S Øresund)
Løbende renholdelse i form af fejning og renhold af dybderender på broer, samt løbende vedligehold og reparationer af beton- og stålkonstruktioner på ca. 40 broer og div. anlægskonstruktioner på A/S Øresunds danske landanlæg. Vedligehold og reparationer udgøres primært af mindre betonreparationer, overfladebehandling af beton- og stålkonstruktioner, reparation af belægning, udskiftning af mindre konstruktionsdele, udskiftning af fuger mv. Alt arbejde udføres langs 12 km og 9 km motorvej.
Se udbuddet » Nævnte leverandører:NCC Roads A/S
2015-12-21HØK, Fornyelse af Helsingør Kraftvarmeværk, B4 Stålkonstruktioner (Helsingør Kraftvarmeværk A/S)
Helsingør Kraftvarmeværk A/S ønsker at forny det eksisterende kraftvarmeværk ved at opføre en et nyt biomassefyret kraftvarmeværk, som placeres i umiddelbar nærhed af det eksisterende kraftvarmeværk på Energivej. Bygge- og anlægsarbejderne udbydes i delentrepriser. Nærværende entreprise omfatter levering og montering af stålkonstruktioner til Røggasrensningsbygningen.
Stålkonstruktioner for røggasrensningsbygning udføres af 6 stålrammer med en højde på 30 meter og en bredde på 19 meter.
Stålrammer er …
Se udbuddet »
2015-12-21HØK, Fornyelse af Helsingør Kraftvarmeværk, B5 Lukning Blokbygning (Helsingør Kraftvarmeværk A/S)
Helsingør Kraftvarmeværk A/S ønsker at forny det eksisterende kraftvarmeværk ved at opføre en et nyt biomassefyret kraftvarmeværk, som placeres i umiddelbar nærhed af det eksisterende kraftvarmeværk på Energivej. Bygge- og anlægsarbejderne udbydes i delentrepriser. Nærværende entreprise omfatter lukning af tag, facade og udvendig kompletterende dele på den ny blokbygning.
Lukning — tag/facade:
Blokbygningen udføres som en regulær bygningskrop, hvor blokbygningens centrale funktioner, kedelrum, …
Se udbuddet »
2015-12-21HØK, Fornyelse af Helsingør Kraftvarmeværk, B2 Betonentreprise (Helsingør Kraftvarmeværk A/S)
Helsingør Kraftvarmeværk A/S ønsker at forny det eksisterende kraftvarmeværk ved at opføre en et nyt biomassefyret kraftvarmeværk, som placeres i umiddelbar nærhed af det eksisterende kraftvarmeværk på Energivej. Bygge- og anlægsarbejderne udbydes i delentrepriser. Nærværende entreprise omfatter Betonarbejderne til Blokbygningen, incl mellembygning.
Se udbuddet » Nævnte leverandører:NCC Danmark A/S
2015-12-21HØK, Fornyelse af Helsingør Kraftvarmeværk, B3 Betonentreprise, brændsel (Helsingør Kraftvarmeværk A/S)
Helsingør Kraftvarmeværk A/S ønsker at forny det eksisterende kraftvarmeværk ved at opføre en et nyt biomassefyret kraftvarmeværk, som placeres i umiddelbar nærhed af det eksisterende kraftvarmeværk på Energivej. Bygge- og anlægsarbejderne udbydes i delentrepriser. Nærværende entreprise omfatter beton- og jordarbejder til bygninger for Brændselshåndtering (Flisgrube, Lagersiloer og Soldhus), fundamenter for transportbånd for flistransport.
Se udbuddet » Nævnte leverandører:Züblin A/S
2015-12-17Etablering af Tissøværket II (Kalundborg Overfladevand A/S)
Kalundborg Overfladevand A/S udbyder hermed etablering af nyt vandværk (Tissø II) til forsyning med overfladevand importeret fra Tissø. Opgaven udbydes i selvstændige deleentrepriser. Der kan ansøges om prækvalifikation på 1 eller flere delentrepriser.
Der udbydes følgende delentrepriser:
B1 Råhus, omfattende jord, kloak, betonarbejder, elementer, stålkonstruktioner samt belægninger og havearbejder
B2 Facade og aptering, omfattende facade- og murerarbejder, tømrer- og snedkerarbejder samt …
Se udbuddet »
2015-12-10RSC Cure NL Lot 3 (DONG Energy Thermal Power A/S)
Cure DONG Energy REnescience B.V. has decided to establish a plant for a complete handling of unsorted household waste (Municipal Solid Waste — MSW).
DONG Energy Thermal Power A/S will be responsible for the execution of the project on behalf of Cure DONG Energy REnescience B.V.
The project, RSC Cure NL will be based on DONG Energy's REnescience Technology, which is a technology for treatment of unsorted household waste. The purpose of the process is sorting and refining the waste for utilization in the …
Se udbuddet »
2015-12-10RSC Cure NL Lot 4 (DONG Energy Thermal Power A/S)
Cure DONG Energy REnescience B.V. has decided to establish a plant for a complete handling of unsorted household waste (Municipal Solid Waste — MSW).
DONG Energy Thermal Power A/S will be responsible for the execution of the project on behalf of Cure DONG Energy REnescience B.V.
The project, RSC Cure NL will be based on DONG Energy's REnescience Technology, which is a technology for treatment of unsorted household waste. The purpose of the process is sorting and refining the waste for utilization in the …
Se udbuddet »
2015-12-10RSC Cure NL LOT 2 (DONG Energy Thermal Power A/S)
Cure DONG Energy REnescience B.V. has decided to establish a plant for a complete handling of unsorted household waste (Municipal Solid Waste — MSW).
DONG Energy Thermal Power A/S will be responsible for the execution of the project on behalf of Cure DONG Energy REnescience B.V.
The project, RSC Cure NL will be based on DONG Energy's REnescience Technology, which is a technology for treatment of unsorted household waste. The purpose of the process is sorting and refining the waste for utilization in the …
Se udbuddet »
2015-11-27HØK, Fornyelse af Helsingør Kraftvarmeværk, B1 Modningsentreprise (Forsyning Helsingør A/S)
Helsingør Kraftvarmeværk A/S ønsker at forny det eksisterende kraftvarmeværk ved at opføre en et nyt biomassefyret kraftvarmeværk, som placeres i umiddelbar nærhed af det eksisterende kraftvarmeværk på Energivej. Bygge- og anlægsarbejderne udbydes i delentrepriser. Nærværende entreprise omfatter modningsarbejderne. Modningsarbejderne omfatter rydning af grund, jordarbejder (15 000 m afgravning, 3 000 m indbygning), etablering af byggeplads til 100 mand, inkl. forsyninger, omlægning af ledninger i jord …
Se udbuddet » Nævnte leverandører:Barslund A/S
2015-10-26AC Off Shore Substation (OSS) topsides for Kriegers Flak (Energinet.dk)
The scope of work includes in particular:
— Fabrication of 3 AC offshore substation topsides for two projects called Kriegers Flak AC and Kriegers Flak CGS app. weight of substation topsides between app. 900 to app. 2 000 Metric tonnes.
The fabrication will be based on detailed design issued by the procuring entities. However, Contractor shall also deliver design where required.
Delivery on sites in the Baltic Sea.
App. outline measures of the largest substation topside: length 46 m, width 33 m, height …
Se udbuddet » Nævnte leverandører:Hollandia Offshore B.V
2015-09-16Energianlæg Aarhus Ø, bygge- og anlægsarbejder (AffaldVarme Aarhus)
AffaldVarme Aarhus har besluttet at opføre en ny kombineret varmepumpe- og vekslerstation på Hjortholmsvej på havnen i Aarhus. Udbuddet omfatter udførelse af bygge- og anlægsarbejder i forbindelse med dette nye energianlæg. Energianlægget forventes udført i spunsgrube. Energianlægget skal pælefunderes og kælder skal udføres i in situ beton. Bygningen areal forventes at blive omkring 900 m. Bygningen forventes udført med; kælder, indskudt dæk, forskellige teknikrum, toilet mv. Over terræn forventes …
Se udbuddet » Nævnte leverandører:EMR Murer & Entreprenør A/SNisgaard+Christoffersen A/S
2015-08-19Kriegers Flak, Øresund and JFK Horizontal Directional Drills (Energinet.dk)
Design and installation of twenty-five horizontal directional drills (HDD) each consisting of 4 pipes prepared for installation of 3 x HV single core cables and 1 x FO cable. The lengths of the drills are in the range 40-450 m and are located on Zeeland and south part of Jutland. Some of the drills will be through coast lines.
The tender includes three lots:
LOT 1: Kriegers Flak Horizontal Directional Drills. Option: After filling of cable duct with Bentonite.
LOT 2: Øresund Horizontal Directional …
Se udbuddet »
2015-08-05Silkeborg Varme A/S, Nye Produktionanlæg — Røggaskondenseringsanlæg (Silkeborg Varme A/S)
Silkeborg Varme A/S skal etablere røggaskondensering på det eksisterende 110 MW gasfyrede kraftvarmeværk med det formål at øge varmeproduktionen med ca. 30 MJ/s. Kontrakten vil blive baseret på et funktionsudbud med et leveringsomfang, der omfatter levering af følgende udstyr og systemer: røggaseconomisere, røggaskondenseringskedler, system til afledning af kondensat, absorptionsvarmepumper, hedtvandsystem til forsyning af varmepumper, gasfyret hedtvandskedel og diverse rørsystemer.
Se udbuddet » Nævnte leverandører:Midroc Automation AB
2015-07-28Centralisering af riste, Renseanlæg Lynetten (BIOFOS A/S)
Udførelse af bygge- og anlægsarbejder, maskin- og smedearbejder, ventilations- og VVS-arbejder og el-installationer i forbindelse med centralisering af riste på Renseanlæg Lynetten.
Der opføres et ny ristehus med riste, findelings- og transportudstyr, containere, udsugning og ventilation, servicefaciliteter m.v.
Det eksisterende ristehus ombygges og renoveres. Det udstyres med nye sandvaskere, ristegodspresser og containere.
Det nye anlæg skal kunne modtage ca. 650 tons ristegods per år mod nu ca. 275 …
Se udbuddet »
2015-06-29Aflæssehal — ombygning for ovnlinje 5 (I/S Nordforbrænding)
Aflæssehallen er en stålbygning placeret op ad affaldssiloen til ovnlinje 4 og tjener som afskærmning for renovationskøretøjernes tømning af affald direkte i siloen fra 4 båse. De bærende konstruktioner udgøres af stålsøjler på pladsstøbte punktfundamenter af beton. Mellem søjler er der gitterdragere pr. ca. 5-6 meter med et spænd på ca. 34 m. Udvendig beklædning er sorte sinusplader i aluminium. Taget er opbygget af profilerede trapezplader med 250 mm kileskåret isolering og 2 lags papdækning.
Se udbuddet » Nævnte leverandører:H. Skjøde Knudsen
2015-05-06Prækvalifikation »Luftpakken«: NOx- og partikelreducerende udstyr til busser (Trafikselskabet Movia)
Movia er Danmarks største trafikselskab med cirka 212 000 000 passagerer om året, 477 buslinjer og ti lokalbanestrækninger. Movia står for planlægningen af bus-, flex- og lokalbanetrafikken i Østdanmark. Movia er som trafikselskab en særlig, lovbestemt offentlig virksomhed beslægtet med et kommunalt fællesskab. Movia betjener og finansieres af Region Hovedstaden, Region Sjælland og de 45 kommuner i de 2 regioner efter lovbestemte regler. Regionerne og kommunerne bestemmer selv, hvor mange buslinjer de …
Se udbuddet » Nævnte leverandører:Amminex Emissions Technology A/SProventia Emission Control Oy
2015-04-24NGF Nature Energy Maansson A/S, Biogas Plant (NGF Nature Energy Månsson A/S)
The tender is for one Biogas Plant, producing biogas from animal manure and other biowaste with a mass
distribution of 75 % to 25 % respectively. The produced biogas is to be upgraded to natural
gasquality in a separate Biogas Upgrading Plant (not part of this tender) and distributed in the Danish natural
gasgrid.
The contract type will be “turn key” including weighing in and receiving station for feedstock to delivery of the
produced biogas to the upgrading plant and facilities for delivery of residual …
Se udbuddet »
2015-04-01Lot M3: Boiler and auxiliary systems (HOFOR Energiproduktion A/S)
Lot M3: Boiler and auxiliary and systems.
The Works includes design, engineering, documentation, fabrication, transportation, construction and commissioning of a complete functional bio-mass fired CFB-boiler plant with nominal fuel input of 500 MW inclusive boiler building and auxiliary and service systems. Fuel is clean woodchips.
Boiler.
Boiler including installations for fuel feeding, deNOx, feed water pumps, ash handling and high pressure piping for steam and feed water.
Auxiliary systems.
Low …
Se udbuddet » Nævnte leverandører:Valmet Technologies Oy
2015-01-30Fjernvarmeforsyning af Dyssrgårdsparken — jord- og smedeentreprise (Dyssegårdsparkens Kraftvarmeværk a.m.b.a.)
Dette er en prækvalifikation i forbindelse med et begrænset udbud. Projektet omhandler en fornyelse af fjernvarmeforsyningen i boligområdet Dyssegårdsparken i Næstved. Entrepriserne omfatter nedtagning/afblænding af gamle forsyningsledninger og etablering af nye forsyningsledninger/stikledninger i jord, samt VVS-arbejder og tillægsydelser i husene i forbindelse med udskiftning af fjernvarmeunits og rørsystem. Arbejdet omfatter 514 husstande, et par institutionsbebyggelser og erhvervsbebyggelser.
Se udbuddet » Nævnte leverandører:Wicotec Kirkebjerg
2015-01-26Prækvalifikation — Levering og montering af nøglefærdigt biogaskraftvarme- og biomassevarmeværk inklusive bygninger... (Lemvig Varmeværk a.m.b.a.)
Annoncen vedrører prækvalifikation til afgivelse af tilbud på et komplet biogasfyret kraftvarmeværk og et kompletfyret biomassefyret varmeværk inklusive bygninger og anlæg i en totalentreprise. Totalentreprisen indeholder en 8,0 MW (indfyret) fliskedel inklusive røgvaskeranlæg og en varmepumpe, et biogas motor-/generatoranlæg med en elektrisk effekt på 3,0 MW inklusive røggassystem og en varmepumpe, to stålskorstene på hver 60 meter og en varmeakkumuleringstank på ca. 5 000 m³ nyttevolumen, samt brovægt, …
Se udbuddet » Nævnte leverandører:Euro Therm A/S
2014-12-16PPP project for the construction of new waste, rainwater and wastewater facilities at Glostrup Hospital (Glostrup Hospital)
Glostrup Hospital calls for tenders for a public-private partnership (PPP) regarding the construction of new facilities for handling and treating waste, rainwater and wastewater at Glostrup Hospital. With the construction of new facilities for rain water, wastewater and waste management Glostrup Hospital wishes to increase utilisation of resources which are today considered waste and wastewater. The facilities are to ensure a financially sustainable future operation of the hospital. The design, …
Se udbuddet »
2014-12-09Prækvalifikation »Luftpakken«: Indkøb, montering, drift og vedlige af SCRT-systemer til busser (Trafikselskabet Movia)
Movia er Danmarks største trafikselskab med cirka 212 000 000 passagerer om året, 477 buslinjer og ti lokalbanestrækninger. Movia står for planlægningen af bus-, flex- og lokalbanetrafikken i Østdanmark. Movia er som trafikselskab en særlig, lovbestemt offentlig virksomhed beslægtet med et kommunalt fællesskab. Movia betjener og finansieres af Region Hovedstaden, Region Sjælland og de 45 kommuner i de to regioner efter lovbestemte regler. Regionerne og kommunerne bestemmer selv, hvor mange buslinjer de …
Se udbuddet »
2014-12-05Etablering af biogasledning, strækning Borris — Ådum, ca 12 km (Bioenergi Vest A/S)
Der søges entreprenør til etablering af biogasledning. Kontrakten omfatter en delstrækning på ca.12 km gasledning fra Borris til Ådum i dimension ø 315 for hovedledning og ø 250 mm for tilsluttende ledninger. Desuden omfattende alle nødvendige arbejder, herunder nødvendige bygværker, levering af gasrør inkl. alle jord- og monteringsarbejder samt alle arbejder ved krydsninger af veje, vandløb mm.
Se udbuddet »
2014-12-05Etablering af biogasledning, strækningen Videbæk — Borris ca. 15 km (Bioenergi Vest A/S)
Der søges entreprenør til etablering af biogasledning. Kontrakten omfatter en delstrækning på ca. 15 km gasledning fra Videbæk til Borris i dimension ø 315 for hovedledning og ø 250 mm for tilsluttende ledninger. Desuden omfattende alle nødvendige arbejder, herunder nødvendige bygværker, levering af gasrør inkl. alle jord- og monteringsarbejder samt alle arbejder ved krydsninger af veje, vandløb mm.
Se udbuddet »
2014-12-01Prækvalifikation: »Luftpakken«: Indkøb, montering, drift og vedlige af SCRT-systemer til busser (Trafikselskabet Movia)
Movia er Danmarks største trafikselskab med cirka 212 millioner passagerer om året, 477 buslinjer og ti lokalbanestrækninger. Movia står for planlægningen af bus-, flex- og lokalbanetrafikken i Østdanmark. Movia er som trafikselskab en særlig, lovbestemt offentlig virksomhed beslægtet med et kommunalt fællesskab. Movia betjener og finansieres af Region Hovedstaden, Region Sjælland og de 45 kommuner i de to regioner efter lovbestemte regler. Regionerne og kommunerne bestemmer selv, hvor mange buslinjer de …
Se udbuddet »
2014-11-27Biomasseanlæg — stål og tag (B03) — biomassefyret kraftvarmeværk i Lisbjerg (Aarhus Kommune, Teknik og Miljø)
Stål- og tagentreprise i forbindelse med etablering af nyt biomassefyret kraftvarmeværk i Lisbjerg.
Entreprise B03 — biomasseanlæg — stål og tag.
Udførelse af leverandørberegning, inklusiv attestering af anerkendt statiker, af stålsamlinger m.m., samt udførelse af: stålkonstruktioner, stålarbejder, tagdækning, ovenlys, samt døre og porte.
(Opmærksomheden henledes i øvrigt generelt til udbud af entreprise B04 — Facader).
Se udbuddet » Nævnte leverandører:Persolit Entreprenørfirma A/S
2014-10-28Horizontal Directional Drills, Thy- Mors-Salling. (HDD TMS) (Energinet.dk)
Design and installation of 8 to 12 horizontal directional drills (HDD) each consisting of 4 pipes prepared for installation of 3 x HV single core cables and 1 x FO cable.
8-12 HDD lengths 300-700 m.
Due to ground conditions it may be required to combine several of the above mentioned HDD's up to a maximum HDD length of 1 500 m.
Se udbuddet »
2014-10-15Aftale om service af vindmøller — Sprogø Havmøllepark (A/S Storebælt)
Service af 7 stk. Vestas V90 3,0 MW mk. 9 vindmøller i Sprogø Havmøllepark. Aftalen omfatter planlagt/ikke planlagt service, samt overvågning af vindmøller. Sejlads til og fra møllerne samt eftersyn og reparation af fundamenter er ikke indeholdt i kontrakten. Ordregiver stiller servicebåd til rådighed.
Se udbuddet » Nævnte leverandører:MHI Vestas Offshore Wind A/S
2014-10-02Bygninger for ovnlinie 5, Kompletteringsentreprisen (I/S Nordforbrænding)
Det samlede byggearbejde omfatter etablering af bygninger i forbindelse med ny Ovnlinje 5, herunder ovnhal og turbinebygning.
Byggeriet er primært en klimaskærm, hvor udformningen af og kravene til bygningerne i høj grad er defineret af den nye ovnlinje (ovn, turbine mv.) der etableres på på stedet samt af arkitekturen af de eksisterende bygninger.
Monteringen af den nye ovnlinje vil ske sideløbende med etablering af bygningerne, hvorfor der ikke kan forventes en kontinuerlig byggeproces især af …
Se udbuddet » Nævnte leverandører:Elindco Byggefirma A/S