2021-02-02Outdoor Wood Chip Storage for AMV4 Lot M1 Mechanical (HOFOR A/S)
Outdoor wood chip storage for AMV4. The contract concerns the design, production and erection of outdoor wood chip storage with conveyer system for AMV4 — Mechanical part. The installations shall be integrated with existing systems at Amagerværket.
Se udbuddet »
2020-08-11Outdoor Wood Chip Storage for AMV4 (1) (HOFOR A/S)
Outdoor wood chip storage for AMV4. The contract concerns the design, production and erection of outdoor wood chip storage with conveyer system for AMV4. The installations shall be integrated with existing systems at Amagerværket.
Se udbuddet »
2020-07-14Outdoor Wood Chips Storage for AMV4 (HOFOR A/S)
Outdoor wood chips storage for AMV4. The contract concerns the design, production and erection of outdoor wood chip storage with conveyer system for AMV4. The installations shall be integrated with existing systems at Amagerværket.
Se udbuddet »
2020-04-30Nyt Aalborg Universitetshospital. E974 Sterilcentral Bufferlager (Region Nordjylland)
Udbuddet vedrører E974 Sterilcentral Bufferlager til Nyt Aalborg Universitetshospital (herefter betegnet bygherre).
Udbuddet omfatter design, specifikation, fabrikation, levering, installation og idriftsættelse af et automatisk buffersystem for sterilvarer på Nyt Aalborg Universitetshospital for effektiv, sikker og hurtig indlagring, buffertering og udlagring af emballerede sterile varer, som er steriliseret i hospitalets steriliseringssystemer til anvendelse på hospitalets afdelinger.
Aftale med den …
Se udbuddet » Nævnte leverandører:Zolvo ApS
2020-01-22Leverancekontrakt vedr. kassetransport- og lagersystem inkl. lagerstyring (WMS) (Region Syddanmark, Projektorganisationen for Nyt OUH)
Den udbudte leverancekontrakt omfatter levering af et nyt logistiksystem til Nyt Odense Universitetshospital (Nyt OUH) i form af et kassetransport- og lagersystem, inkl. lagerstyring (WMS). Region Syddanmark har i 2016-2018 igangsat arbejderne i forbindelse med opførelsen af Nyt OUH ved udbud af byggemodningen (DP01 og DP02) samt ved totalentrepriserne af selve sygehusbyggeriet (DP03, DP04, DP05, DP06, DP07, DP08). Med dette udbud følger nu en tværgående leverancekontrakt vedrørende design, produktion og …
Se udbuddet » Nævnte leverandører:Gibotech A/S
2017-12-15HBS Standard 3 Upgrade - Baggage Handling System (BHS) (Copenhagen Airports A/S)
The Contractor is required to provide a Baggage Handling System (BHS) upgrade to facilitate the installation of ECAC Standard 3 EDS Machines (supplied and installed by others). The new machines will be installed in 3 locations:
— 4 machines in Bag Factory 2,
— 3 machines in the Terminal 3 basement
— 2 machines in the Bag Factory 3
The existing BHS system will be modified as indicated by the tender drawings in order to accomplish the installation of these new machines, including a re-build of the existing …
Se udbuddet »
2015-04-14HØK — Biomass-fired CHP plant — Helsingør — Electromechanical equipment (Helsingør Kraftvarmeværk A/S)
Helsingør Kraftvarmeværk A/S (HØK A/S) is planning a renewal of Helsingør CHP (HØK), establishing a biomass-fired boiler which produces steam to the already existing steam turbine. The fuel is expected to be primary wood chips, but other sustainable biomass resources may also be used. The existing CHP plant will still be able to operate and act as back-up for the new plant as long as appropriate.
The total estimate for the Works is approximately 520 000 000 DKK.
Helsingør Kraftvarmeværk A/S is owned by …
Se udbuddet »
2015-04-01Lot M2: Conveyors and storage system for wood chips (HOFOR Energiproduktion A/S)
Transportation and storage equipment from existing quay to boiler building for wood chips. This includes: Conveyors, transfer points, screeners, magnets, samplers, fire fighting, vacuum cleaning, steel constructions for conveyors, traversing conveyors for loading of A-frame storages, traversing cantilever screws for discharge of A-frame storages, and steel and roof construction for A-frame storages.
Se udbuddet » Nævnte leverandører:Valmet Technologies Oy
2014-12-15Supply and installation of conveyors (Afatek A/S)
Afatek A/S is owned by five public waste management companies, covering the eastern part of Denmark. From its owners, Afatek receive Incinerator Bottom Ash (IBA) which is transported to Afatek's 3 sites for treatment and storage. Afterwards, the bottom ash gravel is used in the construction of roads. Afatek focusses on recovery of ferrous and non-ferrous metals from the IBA. This is partially in order to recover as much metal as possible, but also for the purpose of obtaining a high quality bottom ash …
Se udbuddet » Nævnte leverandører:REMA Anlagenbau Gmbh
2014-05-10Nyt fuldautomatisk varemodtagelsesanlæg samt klargøring til videre intern transport (Herlev Hospital)
Dimensionering og etablering af fuldautomatisk anlæg til håndtering af varer i varemodtagelse og videre transport heraf til interne transportvogne på hospitalet. Systemet skal indeholde transportbånd i plan med gulv, 3 stk. a ca. 25 m, 2 stk. transferkraner for løft mellem stue og kælder, ca. 22 bufferbaner med transportører med plads til ca. 200 transportvogne samt 2 stk. transportkraner for lodret flytning af transportvogne i 2 etager.
Se udbuddet » Nævnte leverandører:Gibotech A/S
2014-03-28Nyt fuldautomatisk affaldstømnings- og vaskeanlæg (Herlev Hospital)
Dimensionering og etablering og indkøring af et fuldautomatisk anlæg til tømning af affaldsvogne og efterfølgende vask. Der forventes at skulle anvendes til 600 liter containere efter DIN 30700/EN 840. Tømme- og vaskekapacitet 20 stk. pr. time, temperatur 65/80 grader celsius. I anlægget indgår bufferpladser på transportører for indløb og udløb ca. 24 stk.
Se udbuddet » Nævnte leverandører:Echberg Manutech ApS
2014-03-28Nyt fuldautomatisk varemodtagelsesanlæg samt klargøring til videre intern transport (Herlev Hospital)
Dimensionering og etablering af fuldautomatisk anlæg til håndtering af varer i varemodtagelse og videre transport heraf til interne transportvogne på hospitalet. Systemet skal indeholde transportbånd i plan med gulv, 3 stk. a ca. 25 m, 2 stk. transferkraner for løft mellem stue og kælder, ca. 22 bufferbaner med transportører med plads til ca. 200 transportvogne samt 2 stk. transportkraner for lodret flytning af transportvogne i 2 etager.
Se udbuddet »
2012-12-19LOT M1: Continuous Ship Unloader (CSU) for wood pellets; LOT M2: Transport and silo discharge equipment for wood... (Vattenfall A/S)
The purchase will be divided into four (4) different lots as described in the following. These may either be ordered as four (4) separate contracts or be freely combined into common contracts.
LOT M1: Continuous Ship Unloader (CSU) for wood pellets.
Supply of one Continuous Ship Unloader (CSU) for wood pellets at Amager Power Station located in the city of Copenhagen.
The supply includes engineering, purchase, manufacturing, installation, commissioning, testing and documentation of one Continuous Ship …
Se udbuddet »
2012-05-23Transport and storage equipment for a biomass co-firing plant for wood pellets (Vattenfall A/S)
The purchase will be divided into two different lots as described in the following. These may either be ordered as two separate contracts or as one common contract.
LOT no. 1: Wood pellet receiving and transport equipment.
The supply includes a wood pellet receiving facility and transport equipment for a biomass co-firing plant for wood pellets located at Nordjyllandsværket in the city of Aalborg.
The supply includes design, manufacturing, supply, installation, testing and commissioning of a wood pellet …
Se udbuddet »