2012-07-04   Overhaul of train engines (LINT 41) - Supply contracts (Lokalbanen A/S)
The Contracting Authority is planning a successive overhaul of the engines of 25 train sets, each containing 2 engines, over the duration of approximately 24 months beginning in November 2012. Each successive overhaul shall be completed in three weeks. Accordingly, please note that it will be a contractual requirement that deliveries take place successively as each train set is disassembled. A time plan will appear from the tender documents. The Contracting Authority will itself perform disassembly and … Se udbuddet »
Nævnte leverandører: EVZ Transmission A/S, CVR no. 27155987