2022-04-01Procurement of steel pipes and hot bends for the Kildedal project (Energinet Teknik og Anlæg A/S)
The tender process concerns a contract for delivery of steel pipes and hot bends for the gas transmission line in relation to the Kildedal project. The pipeline is planned to be established during the spring and summer of 2023. The pipe storage will be divided into minor areas at site which means the supplier must deliver the pipes to several locations by truck. The Kildedal project needs to purchase approximately 2 kilometers of DN400 steel pipes, approximately 500 meters of DN400 HDD and some steel …
Se udbuddet »
2022-03-28Re-routing of 26 km 30” 80 bar Gas Pipeline, West Funen, Denmark (Energinet Teknik og Anlæg A/S)
The decommissioned pipeline and stations will be removed by another contractor. The scope of work comprises the following main activities.
1) Design and construction of approximately 26 km new 30” 80 bar Gas Transmission Pipeline.
2) Design and construction of 3 new Line Valve Stations.
3) Design and construction of cable duct and fibre optical cable along 26 km pipeline including inspection wells for each 5 km.
4) Design and construction of approximately 400 m new 30” 80 bar Gas Transmission Pipeline at …
Se udbuddet » Nævnte leverandører:Per Aarsleff A/S
2022-01-20Framework Agreement concerning M/R stations for Green Gas Lolland-Falster-, Kildedal- and West Funen projects (Energinet Teknik og Anlæg A/S)
The Contracting Authority wants to establish a framework agreement concerning M/R-stations (Measuring & Regulating Stations). The stations are to be used for pressure reduction of natural gas between the transmission pipeline (80-46 barg) and the distribution pipeline (55-12 barg).
The three stations might need to be delivered simultaneously.
The framework agreement concerns potentially three M/R-station for three different projects. The three projects are:
- Green Gas Lolland-Falster: M/R-station …
Se udbuddet » Nævnte leverandører:Bohlen & Doyen Bau GmbH
2021-06-08Udbud af rammeaftale vedrørende svejsearbejder mv. til anlæg og stationer (Energinet Teknik og Anlæg A/S)
Ordregiver ønsker ved etablering af nærværende rammeaftale at have mulighed for at anskaffe en service, hvorunder leverandøren påtager sig at stille kvalificeret mandskab, materiale og udstyr (herunder køretøjer) til rådighed til udførelse af:
— Mekanisk assistance i forbindelse med adskillelse, besigtigelse og kontrol af trykbærende udstyr
— Præfabrikation af rørspools og stålkonstruktioner
— Inspektion og test
— Montagesvejsning, montør mm
— Levering af komponenter og fittings.
Se udbuddet » Nævnte leverandører:EMS ApS
2021-03-05Deodorization Units for Tetrahydrothiophene (THT) Removal from Bio Natural Gas (Energinet Teknik og Anlæg A/S)
In Denmark, the amount of biogas on the distribution grids increases. When bio natural gas (biomethane) from distribution grids is fed into the transmission grid, the concentration of odorant present in the gas needs to be reduced to trace amounts before the gas enters the transmission grid. The removal of the odorant, tetrahydrothiophene (THT), will be executed by a deodorization unit, at the place of injection into the transmission system. The tendered assignment is the supply and installation of one …
Se udbuddet »
2021-03-01Investigations for Marine Crossings – Green Gas Lolland-Falster (GGLF) (Energinet Teknik og Anlæg A/S)
The Green Gas Lolland-Falster (GGLF) project will facilitate transport of gas from Zealand to the sugar factories in Lolland and Falster. For this a new gas pipeline is planned. In connection to this gas pipeline there will be three marine crossings in which Horizontal directional drilling (HDD) needs to be carried out. The assignment is divided into 2 lots:
Lot 1: WPA: Offshore geophysical survey; and
Lot 2: WPB: On- and offshore geotechnical boreholes, refractions seismic survey and Electrical …
Se udbuddet »
2021-02-05Commissioning Manager for the Baltic Pipe Project at the Compressor Station Everdrup (Energinet Teknik og Anlæg A/S)
The commissioning manager will – in collaboration with project management for Everdrup compres-sor station – be responsible for ensuring that the overall requirements of the project are implemented and complied with during the execution of the work. The commissioning manager is responsible for ensuring compliance with the Baltic Pipe project’s overall commissioning strategy and associated schedule in the ‘Everdrup compressor station’ project. Organisationally, the commissioning manager will be reporting …
Se udbuddet »
2020-08-27Udbud af kontrakt vedr. vedligehold af grønne arealer til Energinet Teknik og Anlæg A/S (Energinet Teknik og Anlæg A/S)
Den udbudte opgave omfatter 2 delaftaler vedr. vedligehold af ordregivers grønne arealer på stationsarealer i hhv. Jylland og Fyn samt på Sjælland. Opgaven omfatter ordregivers anskaffelse af græsklipning, fejning og renholdelse af flisebelægning, rydning af vegetation, hegnsklipning, beskæring af træer og buske, sprøjtning for ukrudt og vedligeholdelse af bevoksning ud mod tredjeparter på ordregivers lokationer.
Se udbuddet » Nævnte leverandører:Grøn Vækst A/S
2020-06-25Udbud af kontrakt vedr. vedligehold af grønne arealer til Energinet Teknik og Anlæg A/S (Energinet Teknik og Anlæg A/S)
Den udbudte opgave omfatter 2 delaftaler vedr. vedligehold af ordregivers grønne arealer i hhv. Jylland og Fyn samt på Sjælland. Opgaven omfatter ordregivers anskaffelse af græs-klipning, fejning og renholdelse af flisebelægning, rydning af vegetation, hegnsklipning, beskæring af træer og buske, sprøjtning for ukrudt og vedligeholdelse af bevoksning ud mod tredjeparter på ordregivers lokationer.
Se udbuddet »
2020-05-27Deodorisation Unit for Tetrahydrothiophene (THT) Removal from Bio Natural Gas (Energinet Teknik og Anlæg A/S)
In Denmark, the amount of bio gas on the distribution grids increases. When bio natural gas (biomethane) from distribution grids is fed into the transmission grid, the concentration of odorant present in the gas needs to be reduced to trace amounts before the gas enters the transmission grid. The removal of the odorant, tetrahydrothiophene (THT), will be executed by a deodorisation unit at the place of injection into the transmission system. The tendered assignment is the supply and installation of a …
Se udbuddet » Nævnte leverandører:Bilfinger EMS GmbH
2019-12-19Deodorization Units for Tetrahydrothiophene (THT) Removal from Bio Natural Gas (Energinet Teknik og Anlæg A/S)
In Denmark, the amount of biogas on the distribution grids increases. When bio natural gas (biomethane) from distribution grids is fed into the transmission grid, the concentration of odorant present in the gas needs to be reduced to trace amounts before the gas enters the transmission grid. The removal of the odorant, tetrahydrothiophene (THT), will be executed by a deodorization unit, at the place of injection into the transmission system. The tendered assignment is the supply and installation of 2 …
Se udbuddet » Nævnte leverandører:Bilfinger EMS GmbH
2018-10-26Framework Agreement for Gas Compressor Packages (Energinet Teknik og Anlæg A/S)
Energinet tenders for a Framework Agreement for compressors for injection of upgraded biogas into the 19/40 barg distribution grid or the 80 barg natural gas transmission grid in Denmark.
The compressor packages will have different requirements to capacity range as well as pressure range. Basically, the units shall cover the capacity range from 500 Nm3/hr to 6 000 Nm3/hr, with an inlet pressure of approx. either 4, 7, 19 or 40 barg and an outlet pressure of approx. 19, 40 or 80 barg. They shall be …
Se udbuddet » Nævnte leverandører:Arizaga, Bastarrica Y CiaFornovogas SrlKwangshin Machine Ind. Co. Ltd
2018-09-20Framework Agreement for Gas Compressor Packages (Energinet Teknik og Anlæg A/S)
Energinet tenders for a Framework Agreement for compressors for injection of upgraded biogas into the 19/40 barg distribution grid or the 80 barg natural gas transmission grid in Denmark.
The compressor packages will have different requirements to capacity range as well as pressure range. Basically, the units shall cover the capacity range from 500 Nm3/hr to 6 000 Nm3/hr, with an inlet pressure of approx. either 4, 7, 19 or 40 barg and an outlet pressure of approx. 19, 40 or 80 barg. They shall be …
Se udbuddet »