De seneste indkøb af kabellægning med kabelskibe i Danmark
2016-12-08Kriegers Flak Combined Grid Solution Burial and Protection of 150 kV Submarine Cables (Energinet.dk)
Kriegers Flak CGS (Combined Grid Solution) is a joint project between Energinet.dk and 50Hertz Transmission to interconnect the Danish and German grid via the two offshore wind farms at Krieger's Flak (DK) and Baltic 2 (DE). The Contracting Entity wants to procure Burial and Protection of approximately 2 x 24 km of submarine cable route, which is to be divided into trenching and jetting work for the Krieger's Flak CGS connection. The works includes inter alia:
1. Boulder Removal
2. …
Se udbuddet »