2017-09-15   Onshore Grid for Vesterhav Nord and Vesterhav Syd (Vattenfall Vindkraft Vesterhav Syd P/S; Vattenfall Vindkraft Vesterhav Nord P/S)
Supply of all required work for the Onshore Grid corresponding to the 66 kV Cable supply, cable installation, onshore substation building including 66 kV equipment and its facilities corresponding to the requirements specified by the contracting entities and for both Vesterhav Nord and Vesterhav Syd. The Onshore Grid for both sites, Vesterhav Nord and Vesterhav Syd, will consist of: — Two 66 kV onshore cable systems, — One 66 kV onshore Substation. Vattenfall has been awarded the concession for the … Se udbuddet »
Nævnte leverandører: Per Aarsleff A/S
2016-07-20   Installation of Medium voltage system on OSS of DKF (Vattenfall Vindkraft A/S)
The engineering, supply and install of the MV-system (using Employer provided components), incl. supply of the telecommunication equipment, cables and accessories on the Offshore Substations (OSS's) of the Offshore windfarm Kriegers Flak. Se udbuddet »
2016-04-15   RSC Cure NL LOT 1 — Civil Works (DONG Energy Thermal Power A/S)
Cure DONG Energy REnescience B.V. has decided to establish a plant for a complete handling of unsorted Se udbuddet »
2014-07-15   Drifts og Anlægsydelser 2015+ (DONG Energy Sales & Distribution A/S)
Målet med rammeaftalen. Indkøbet er en del af DONG Energy's strategi om at få leveret hovedparten af vores entreprenør- og serviceydelser fra få faste leverandører. Disse faste leverandører skal alle kunne levere alle typer af ydelser, og således også koordinere og styre de nødvendige fagentrepriser. Denne udbudsbekendtgørelse udsendes efter en forudgående RFI-aktivitet annonceret på www.udbud.dk Indkøbet har som formål at udvælge 2 faste partnere og en fast projektpartner. De 2 faste partnere tildeles … Se udbuddet »