Three (3) HDD installation for the project GGLF (Green Gas Lolland Falster). The three crossings are world-class as they are long and deep, and working under strict environmental conditions. The Scope of Works will be considered to cover all phases of work from design maturation to installation, testing and pre-commissioning.
Deadline
Fristen for modtagelse af bud var på 2022-04-25.
Indkøbet blev offentliggjort på 2022-04-08.
Leverandører
Følgende leverandører er nævnt i tildelingsbeslutninger eller andre indkøbsdokumenter:
Three (3) HDD installation for the project GGLF (Green Gas Lolland Falster). The three crossings are world-class as they are long and deep, and working under strict environmental conditions. The Scope of Works will be considered to cover all phases of work from design maturation to installation, testing and pre-commissioning.
Vis mere
Anslået værdi uden moms: EUR 20 000 000 💰
The tender concerns the installation of steel pipe on three sections of the Green Gas Lolland-Falster gas pipeline project. The sections in this scope of work cross three marine crossings, and will be in-stalled using the ‘HDD’ technique, whereby the entire length of pipe will be pulled as a string through a sub-surface hole prepared using ‘Horizonal Directional Drilling’.
The three HDD covers construction of the following:
• HDD crossing of Færgestrøm: approximately 1884 m long 10” steel pipeline
• HDD crossing of Grønsund: approximately 1925 m long 10” steel pipeline
• HDD crossing of Guldborgsund: 1255 m long 10” steel pipeline
The HDD trajectory is expected to be through soft chalk, which is dominant in this region. The thickness of the chalk on these crossings is 10’s of meters. The onset of the chalk is between 5-20m on the landfall sections of the project where the HDD begins and ends. Soil layering above the chalk is typical of this area, with post-glacial tills, overlaid or interbedded with post-glacial clays, silt and sands. Flint is present in the region, and from the soil investigations carried out on these crossings seen to represent approximately 1-2% of the total rock volume sampled in the geotechnical borehole program. Boulders are present in the till layers.
The phase of work include detailed design, installation and testing of these sections of the pipeline from initial site preparation, through pre-commissioning. The work is complete when the pipe is suc-cessfully installed, filled with nitrogen gas, and sealed, ready for tie-in to the land-line and the rest of the pipeline.
For further information regarding the tendered contract and the scope of work the Contracting Authority refers to the Tender Document package, including Particular Specifications (doc. no. 21/09717-27).
Vis mere Kriterier for tildeling
Prisen er ikke det eneste tildelingskriterium, og alle kriterier er kun anført i udbudsdokumenterne
Omfanget af udbuddet
Anslået samlet værdi ekskl. moms: EUR 20 000 000 💰
Kontraktens, rammeaftalens eller det dynamiske indkøbssystems varighed
Nedenstående tidsramme er udtrykt i antal måneder.
Beskrivelse
Varighed: 18
Oplysninger om begrænsningerne i antallet af ansøgere, der kan indbydes
Påtænkt minimumsantal: 3
Maksimalt antal: 5
Objektive kriterier for udvælgelse af det begrænsede antal ansøgere:
“If more than 3 applicants fulfill the minimum requirements, cf. section III, the Contracting Authority will prequalify the up to 5 applicants who are...”
Objektive kriterier for udvælgelse af det begrænsede antal ansøgere
If more than 3 applicants fulfill the minimum requirements, cf. section III, the Contracting Authority will prequalify the up to 5 applicants who are evaluated as most qualified for the specific tendered assign-ment. Only these applicants will be invited to submit a tender. The selection of the applicants will be based on the relevance of the submitted references, cf. the scope stated in section II.2.4, and the extent to which the references overall demonstrate comprehensive experience with deliveries comparable to the tendered assignment regarding solution, complexity and scope, especially concerning:
• References concern HDD projects of a similar or longer distance than in the current project.
• References concern HDD under similar soil conditions to the current project, including;
o Soft chalk
o Post-glacial tills, overlaid or interbedded with post-glacial clays, silt and sands.
o Flint
o Boulders
• References relate to projects with focus on environmental protection from noise, pollution and light;
• References with the use of the intersect method, where twinned drilling rigs are used for crossings 1500-2000m;
• References demonstrating operational capacity for ‘large’ HDD rigs in excess of 250 tons.
• References concern installation of steel pipes with a similar or higher diameter than in the current project;
Vis mere Beskrivelse
Yderligere oplysninger:
“This is a negotiated procedure. With exception of mandatory parts, the Tender Documents may undergo changes as part of the negotiation process.CA serve the...”
Yderligere oplysninger
This is a negotiated procedure. With exception of mandatory parts, the Tender Documents may undergo changes as part of the negotiation process.CA serve the right to update the tendered time schedule during the tender procedure due to delay in permits, approvals, expropriation, archeology site investigations etc.
Juridiske, økonomiske, finansielle og tekniske oplysninger Økonomisk og finansiel stilling
Liste og kortfattet beskrivelse af udvælgelseskriterier:
“The applicant must confirm the economic ability in the ESPD part IV.B: “Economic and financial standing” with information from the latest annual report...”
Liste og kortfattet beskrivelse af udvælgelseskriterier
The applicant must confirm the economic ability in the ESPD part IV.B: “Economic and financial standing” with information from the latest annual report regarding the following economic indicators:
1. Equity (total equity incl. share capital, reserves, revaluation, retained earning etc.)
2. Equity ratio (equity/total assets). This must be stated with two decimals.
If the applicant is relying on the capacities of one or more other entities (e.g. a parent or sister com-pany or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the information for the ESPD part IV.B must also be given in a separate ESPD from each of these entities, cf. section VI.3 “Additional information”. It is the sole responsibility of the applicant to secure that the minimum level(s) of standards required are reached on the basis of consolidation when the applicant is relying on the capacity of other entities or when the applicant is a group of economic operators (e.g. a consortium).
“Concerning 1: Equity from the latest annual report must, at the time of prequalification, be at least 6,600,000 EUR.
Concerning 2: Equity ratio from the...”
Concerning 1: Equity from the latest annual report must, at the time of prequalification, be at least 6,600,000 EUR.
Concerning 2: Equity ratio from the latest annual report must, at the time of prequalification, be at least 20 pct. If the equity ratio is between 15 pct. and 20 pct. the applicant can qualify if Equity ex-ceeds 20,000,000 EUR.
Vis mere Teknisk og faglig kompetence
Liste og kortfattet beskrivelse af udvælgelseskriterier:
“The applicant must include the up to 5 most comparable and relevant references undertaken in the past five 5 years as part of the application. The...”
Liste og kortfattet beskrivelse af udvælgelseskriterier
The applicant must include the up to 5 most comparable and relevant references undertaken in the past five 5 years as part of the application. The references must be stated in the ESPD part IV.C: “Technical and professional ability”. Undertaken in the past five 5 years implies that the reference must not have been completed prior to the date reached when counting 5 years backwards from the submission date for prequalification. References older than this will not be taken into consideration. References which have not yet been fully completed can be included as part of the application, but if this is the case, the applicant must describe the parts which have not yet been delivered, and this may affect the evaluation of the applicant, cf. section II.2.9.
The references should include:
• A specific description of the work performed for each reference, including 1) length and purpose of the HDD, 2) type, measure and dimensions of the installed pipe, 3) soil conditions, 4) applied equipment (single rigs, dual rigs with intersection, …), 5) environmental protection measures (e.g protection from noise, pollution and light), 6) intersect method, and 7) operational capacity of rigs used
• Contract complexity: principle sub-contractors should be listed, with summary scope if possible.
• Contract value (if possible)
• Contact information for the entity in question (including contact person)
• Date of initiation and final delivery (day, month, year)
Any ambiguities and/or incomprehensibilities concerning the above information may have a negative effect on the selection of candidates, cf. section II.2.9. Please note the “description” box can contain more text than is visible. I.e. it is possible to copy paste text into the box.
If the applicant is relying on the references of one or more other entities (e.g. a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the information for the ESPD part IV.C must also be given in a separate ESPD from each of these entities.
The number of references should not surpass a maximum of the 5 most comparable and relevant references. If the applicant is relying on the capacity of one or more other entities (e.g. a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the maximum number of references to be submitted must still be respected and cannot exceed 5 when combined. If more than 5 references are submitted, the Contracting Authority will only consider the 5 most recent references determined by date of final delivery (in this case not yet finished references will not be included).
Vis mere Betingelser for deltagelse
Liste og kortfattet beskrivelse af regler og kriterier:
“The applicant must submit a completed version of the ESPD.
Applicants may not be subject to the mandatory grounds for exclusion, cf. the Danish Public...”
Liste og kortfattet beskrivelse af regler og kriterier
The applicant must submit a completed version of the ESPD.
Applicants may not be subject to the mandatory grounds for exclusion, cf. the Danish Public Procurement Act (udbudsloven) Section 135 (1-3) and 136.
Please see section VI.3 “Additional information” for further information regarding the ESPD. The application must be submitted through EU-Supply, cf. link in section I.1 in this notification. Applications not submitted via EU-supply or received after the deadline will not be accepted.
The Contracting Authority reserves the right to request the applicant to supplement, specify or complete the information submitted.
Vis mere
Krav om deponering og sikkerhedsstillelse: The information is stated in the Tender Documents.
De vigtigste finansieringsbetingelser og betalingsordninger og/eller henvisning til de relevante bestemmelser, der regulerer dem: The information is stated in the Tender Documents.
Den juridiske form, som den sammenslutning af økonomiske aktører, der skal have kontrakten, skal have:
“No special legal form is required.
If the agreements are awarded to a group of economic operators (e.g. a consortium) the participants are required to...”
Den juridiske form, som den sammenslutning af økonomiske aktører, der skal have kontrakten, skal have
No special legal form is required.
If the agreements are awarded to a group of economic operators (e.g. a consortium) the participants are required to undertake joint and several liabilities and to appoint one economic operator to represent the group.
Vis mere Betingelser i forbindelse med kontrakten
Betingelser for opfyldelse af kontrakten: The information is stated in the Tender Documents.
Procedure Type af procedure
Forhandlet procedure med forudgående indkaldelse af konkurrencer
Oplysninger om reduktion af antallet af løsninger eller tilbud under forhandling eller dialog
Anvendelse af en trinvis procedure for gradvist at reducere antallet af løsninger, der skal drøftes, eller af tilbud, der skal forhandles
Administrative oplysninger
Frist for modtagelse af bud eller ansøgninger om deltagelse: 2022-04-25
12:00 📅
Sprog, på hvilke bud eller ansøgninger om deltagelse kan indgives: engelsk 🗣️
Nedenstående tidsramme er udtrykt i antal måneder.
Minimumsfrist, inden for hvilken tilbudsgiveren skal opretholde tilbuddet: 18
Supplerende oplysninger Oplysninger om elektroniske arbejdsgange
Elektronisk fakturering vil blive accepteret
Der vil blive anvendt elektronisk betaling
Yderligere oplysninger
“The applicant must submit a completed ESPD to apply for prequalification for this tender procedure. The ESPD for this tender can be found via EU-supply. The...”
The applicant must submit a completed ESPD to apply for prequalification for this tender procedure. The ESPD for this tender can be found via EU-supply. The ESPD must be completed in EU-Supply and submitted via “My Response”. A guide to the ESPD can be found on the webpage of the Competition and Consumer Authority (www.kfst.dk) in Danish (the Contracting Authority is not responsible for the content of the guide).
Please note:
- An applicant participating on its own, but relying on the capacities of one or more other entities (e.g. a parent or sister company or a subcontractor), must ensure that the application includes the applicants own ESPD together with a separate ESPD from each of the entities it relies on with a completed part II: “Information concerning the economic operator” and part III: “Exclusion grounds” of the ESPD as well as the relevant information regarding part IV: “Selection criteria” and part V: “Reduction of the number of qualified candidates”. The ESPD from each of the entities should be duly filled and signed by the entities concerned.
Further where an applicant wants to rely on the capacities of other entities, it shall prove to the contracting authority that it will have at its disposal the resources necessary, for example, by producing a commitment by those entities to that effect, which must be submitted as part of the final documentation.
- Where groups of economic operators, including temporary associations, participate together in the procurement procedure, a complete separate ESPD for each of the participating economic operators must be submitted.
Further the final documentation must include a signed declaration by all parties of the group of economic operators (joint venture, consortium or other) stating that all economic operators as-sume joint and several liabilities towards the Contracting Authority for the performance of the contract as a whole.
Bekendtgørelse om indgåede kontrakter (2023-01-12) Objekt Omfanget af udbuddet
Samlet værdi af indkøbsaftalen (ekskl. moms): EUR 24 111 760 💰
Procedure Administrative oplysninger
Tidligere offentliggørelse vedrørende denne procedure: 2022/S 073-196662
Tildeling af kontrakt
1️⃣
Kontraktnummer: 1
Titel: GGLF (Green Gas Lolland Falster) – 3 HDD’s
Dato for indgåelse af kontrakten: 2023-01-02 📅
Oplysninger om udbud
Kontrakten er blevet tildelt en gruppe af økonomiske aktører ✅ Navn og adresse på kontrahenten
Navn: Spiecapag
Nationalt registreringsnummer: 399237494
Postadresse: 2313 Boulevard de la Défense
Postby: Nanterre
Postnummer: 92000
Land: Frankrig 🇫🇷
Region: France 🏙️
Entreprenøren er en SMV
Navn: Horizontal Drilling International S.A.S.
Nationalt registreringsnummer: 388 835 308 R.C.S.
Postadresse: 2313 Boulevard de la Défense,
Entreprenøren er en SMV ✅
Navn: MT Højgaard Danmark A/S
Nationalt registreringsnummer: 12 56 22 33
Postadresse: Knud Højgaards Vej 7
Postby: Søborg
Postnummer: 2860
Land: Danmark 🇩🇰
Region: Danmark🏙️ Oplysninger om kontraktens/parcellens værdi (ekskl. moms)
Kontraktens/parcellens samlede værdi: EUR 24 111 760 💰
Kilde: OJS 2023/S 012-030642 (2023-01-12)