Strategic Environmental Assessment (SEA) and Environmental Investigations for Offshore Wind Farms and Energy Islands in the North Sea and the Baltic Sea
With the climate agreement for energy and industry of the 22 June 2020 the majority of the Danish Parliament decided that Denmark will become the first country in the world to begin the construction of two energy island with a total capacity of 5 GW offshore wind.
One of the islands will be located in the North Sea with a capacity of 3 GW. This island can be further scaled up to 10 GW offshore wind. The other energy island will be established on the current island of Bornholm with a capacity of 2 GW. The islands are scheduled for completion by 2030.
Following the political decision, the Danish Energy Agency has instructed the Energinet to initiate site investigations, environmental and metocean studies and analysis for grid connection for the area of investigation.
Deadline
Fristen for modtagelse af bud var på 2021-03-23.
Indkøbet blev offentliggjort på 2021-03-03.
Leverandører
Følgende leverandører er nævnt i tildelingsbeslutninger eller andre indkøbsdokumenter:
Objekt Omfanget af udbuddet
Titel:
“Strategic Environmental Assessment (SEA) and Environmental Investigations for Offshore Wind Farms and Energy Islands in the North Sea and the Baltic Sea
21/01698”
Titel
Strategic Environmental Assessment (SEA) and Environmental Investigations for Offshore Wind Farms and Energy Islands in the North Sea and the Baltic Sea
21/01698
Vis mere
Produkter/tjenester: Rådgivning i forbindelse med miljøteknik📦
Kort beskrivelse:
“With the climate agreement for energy and industry of the 22 June 2020 the majority of the Danish Parliament decided that Denmark will become the first...”
Kort beskrivelse
With the climate agreement for energy and industry of the 22 June 2020 the majority of the Danish Parliament decided that Denmark will become the first country in the world to begin the construction of two energy island with a total capacity of 5 GW offshore wind.
One of the islands will be located in the North Sea with a capacity of 3 GW. This island can be further scaled up to 10 GW offshore wind. The other energy island will be established on the current island of Bornholm with a capacity of 2 GW. The islands are scheduled for completion by 2030.
Following the political decision, the Danish Energy Agency has instructed the Energinet to initiate site investigations, environmental and metocean studies and analysis for grid connection for the area of investigation.
Vis mere
Anslået værdi uden moms: EUR 6 000 000 💰
Oplysninger om partier
Der kan afgives bud for alle partier
Maksimalt antal partier, der kan tildeles én tilbudsgiver: 1
1️⃣ Omfanget af udbuddet
Titel:
“Strategic Environmental Assessment (SEA) and Environmental Investigations for Offshore Wind Farms and Energy Islands in the North Sea” Titel
Partiets identifikationsnummer: 1
Beskrivelse
Yderligere produkter/tjenester: Rådgivning i forbindelse med miljøteknik📦
Yderligere produkter/tjenester: Miljøvurdering i forbindelse med bygge- og anlægsarbejder📦
Sted for udførelsen: Danmark🏙️
Hovedsted eller sted for udførelsen:
“The North Sea The investigation area – which is located approximately 100 km west of Harboøre (Jutland) – and at Energinets and Consultants offices.”
Beskrivelse af udbuddet:
“A broad coalition of Danish parties decided on 22 June 2020 to initiate the realization of two energy islands:
In the North Sea, as an artificial island,...”
Beskrivelse af udbuddet
A broad coalition of Danish parties decided on 22 June 2020 to initiate the realization of two energy islands:
In the North Sea, as an artificial island, which will serve as a hub for offshore wind farms with a total capacity of 3 GW and potentially up to 10 GW in the future.
In the Baltic Sea, the Island of Bornholm will be the physical hub for offshore wind farms with a total capacity of 2 GW.
Both energy islands will export power to the mainland of Denmark and neighboring countries and are intended to serve as a hub that collects electricity from the surrounding offshore windfarms and distributes the electricity between countries via electricity grid connections.
One of the islands will be located in the North Sea with a capacity of 3 GW, and this island will be extended in stages as the construction of new international connections to neighboring countries are developed, and the demand of power will increase. In the future, the island can be further scaled up to 10 GW offshore wind. The other energy island will be established on the current island of Bornholm with a capacity of 2 GW.
Following the political decision, the Danish Energy Agency has instructed the Energinet to initiate site investigations, environmental and metocean studies and analysis for grid connection for the area of investigation. The current tender (lot 1) concerns consultancy services for preparing environmental assessments, planning consents and marine environmental baseline investigations for an energy island with surrounding offshore wind farms in the North Sea.
The current tender concerns consultancy services for preparing environmental assessments, planning consents and marine environmental baseline investigations for two energy islands and offshore wind projects in Denmark.
For further details concerning the purchase, reference is made to the scope of services.
The tendered assignment is divided into 2 lots. Lot 1 concerns the North Sea and lot 2 concerns the Baltic Sea. Tenderers applying for pre-qualification will apply for both lot 1 and lot 2. Regardless of the tenderers being pre-qualified for lot 1 and lot 2, a tenderer will maximum be awarded one (1) lot. Lot 1 will be prioritized, and the Tenderer awarded lot 1 will therefore have its tender-offer for lot 2 taken out of the evaluation for lot 2.
For further details concerning the purchase, reference is made to the scope of services and the rest of the tender material.
Vis mere Kriterier for tildeling
Prisen er ikke det eneste tildelingskriterium, og alle kriterier er kun anført i udbudsdokumenterne
Omfanget af udbuddet
Anslået samlet værdi ekskl. moms: EUR 3 000 000 💰
Kontraktens, rammeaftalens eller det dynamiske indkøbssystems varighed
Nedenstående tidsramme er udtrykt i antal måneder.
Beskrivelse
Varighed: 48
Oplysninger om begrænsningerne i antallet af ansøgere, der kan indbydes
Påtænkt antal ansøgere: 4
Objektive kriterier for udvælgelse af det begrænsede antal ansøgere:
“The contracting authority will prequalify 4 applicants in total for the two (2) lots.
If more than 4 applicants fulfills the minimum requirements, cf....”
Objektive kriterier for udvælgelse af det begrænsede antal ansøgere
The contracting authority will prequalify 4 applicants in total for the two (2) lots.
If more than 4 applicants fulfills the minimum requirements, cf. section III, the contracting authority will pre-qualify the 4 applicants who are evaluated as most qualified for the specific tendered assignment. Only these applicants will be invited to submit a tender. The selection of the applicants will be based on the submitted references. That is to which extend the reference(s) are assed to be similar to the tendered assignment, cf. section II.2.4), in terms of comparability and relevance. As a result, the number of references will not be the determining factor alone, but more importantly to which degree the specific forwarded references are comparable and relevant to the tendered assignment regarding solution and scope.
The following will be evaluated as positive:
• the references are of similar types of project in contents and extent of investigations;
• the references cover relevant environmental/technical topics, preferably both onshore and offshore, in relation to the tendered assignment such as impact assessments of an infrastructure project covering marine mammals, birds, navigational safety (incl. HAZID workshop), constraint analysis and visibility assessment;
• the references show a solid experience in environmental survey and assessment of major offshore projects, including interaction with environmental authorities and Danish Environmental legislation.
Vis mere Beskrivelse
Yderligere oplysninger:
“Please note that this is a negotiated procedure. With the exception of mandatory parts, the tender documents may as a result undergo changes as part of the...”
Yderligere oplysninger
Please note that this is a negotiated procedure. With the exception of mandatory parts, the tender documents may as a result undergo changes as part of the negotiation process.
2️⃣ Omfanget af udbuddet
Titel:
“Strategic Environmental Assessment (SEA) and Environmental Investigations for Offshore Wind Farms and Energy Islands in the Baltic Sea” Titel
Partiets identifikationsnummer: 2
Beskrivelse
Hovedsted eller sted for udførelsen:
“The Baltic Sea The investigation area – which is located approximately 20 km south/west of Bornholm (The Baltic Sea) – and at Energinets and Consultants offices.”
Hovedsted eller sted for udførelsen
The Baltic Sea The investigation area – which is located approximately 20 km south/west of Bornholm (The Baltic Sea) – and at Energinets and Consultants offices.
Vis mere
Beskrivelse af udbuddet:
“A broad coalition of Danish parties decided on 22 June 2020 to initiate the realization of two energy islands:
In the North Sea, as an artificial island,...”
Beskrivelse af udbuddet
A broad coalition of Danish parties decided on 22 June 2020 to initiate the realization of two energy islands:
In the North Sea, as an artificial island, which will serve as a hub for offshore wind farms with a total capacity of 3 GW and potentially up to 10 GW in the future.
In the Baltic Sea, the Island of Bornholm will be the physical hub for offshore wind farms with a total capacity of 2 GW.
Both energy islands will export power to the mainland of Denmark and neighboring countries and are intended to serve as a hub that collects electricity from the surrounding offshore windfarms and distributes the electricity between countries via electricity grid connections.
One of the islands will be located in the North Sea with a capacity of 3 GW, and this island will be extended in stages as the construction of new international connections to neighboring countries are developed, and the demand of power will increase. In the future, the island can be further scaled up to 10 GW offshore wind. The other energy island will be established on the current island of Bornholm with a capacity of 2 GW.
Following the political decision, the Danish Energy Agency has instructed the Energinet to initiate site investigations, environmental and metocean studies and analysis for grid connection for the area of investigation. The current tender (lot 2) concerns consultancy services for preparing environmental assessments, planning consents and marine environmental baseline investigations for an energy island with surrounding offshore wind farms in the Baltic Sea.
The current tender concerns consultancy services for preparing environmental assessments, planning consents and marine environmental baseline investigations for two energy islands and offshore wind projects in Denmark.
For further details concerning the purchase, reference is made to the scope of services.
The tendered assignment is divided into 2 lots. Lot 1 concerns the North Sea and lot 2 concerns the Baltic Sea. Tenderers applying for pre-qualification will apply for both lot 1 and lot 2. Regardless of the tenderers being pre-qualified for lot 1 and lot 2, a tenderer will maximum be awarded one (1) lot. Lot 1 will be prioritized, and the Tenderer awarded lot 1 will therefore have its tender-offer for lot 2 taken out of the evaluation for lot 2.
For further details concerning the purchase, reference is made to the scope of services and the rest of the tender material.
Vis mere Omfanget af udbuddet
Anslået samlet værdi ekskl. moms: EUR 3 000 000 💰
Oplysninger om begrænsningerne i antallet af ansøgere, der kan indbydes
Objektive kriterier for udvælgelse af det begrænsede antal ansøgere:
“The contracting authority will pre-qualify 4 applicants in total for the two (2) lots.
If more than 4 applicants fulfill the minimum requirements, cf....”
Objektive kriterier for udvælgelse af det begrænsede antal ansøgere
The contracting authority will pre-qualify 4 applicants in total for the two (2) lots.
If more than 4 applicants fulfill the minimum requirements, cf. section III, the contracting authority will prequalify the 4 applicants who are evaluated as most qualified for the specific tendered assignment. Only these applicants will be invited to submit a tender. The selection of the applicants will be based on the submitted references. That is to which extend the reference(s) are assed to be similar to the tendered assignment, cf. section II.2.4), in terms of comparability and relevance. As a result, the number of references will not be the determining factor alone, but more importantly to which degree the specific forwarded references are comparable and relevant to the tendered assignment regarding solution and scope.
The following will be evaluated as positive:
• the references are of similar types of project in contents and extent of investigations;
• the references cover relevant environmental/technical topics, preferably both onshore and offshore, in relation to the tendered assignment such as impact assessments of an infrastructure project covering marine mammals, birds and bats, navigational safety (incl. HAZID workshop), constraint analysis and visibility assessment;
• the references show a solid experience in environmental survey and assessment of major offshore projects, including interaction with environmental authorities and Danish Environmental legislation.
Juridiske, økonomiske, finansielle og tekniske oplysninger Økonomisk og finansiel stilling
Liste og kortfattet beskrivelse af udvælgelseskriterier:
“The applicant must confirm the economic ability in the ESPD part IV.B: ‘Economic and financial standing’ with information from the latest annual report...”
Liste og kortfattet beskrivelse af udvælgelseskriterier
The applicant must confirm the economic ability in the ESPD part IV.B: ‘Economic and financial standing’ with information from the latest annual report regarding the following economic indicators:
1) Equity (total equity incl. share capital, reserves, revaluation, retained earning etc.);
2) Equity ratio (equity/total assets).
If the applicant is relying on the capacities of one or more other entities (e.g. a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the information for the ESPD part IV.B must also be given in a separate ESPD from each of these entities, cf. section VI.3) ‘Additional information’. It is the sole responsibility of the applicant to secure that the minimum level(s) of standards required are reached when the applicant is relying on the capacity of other entities or when the applicant is a group of economic operators (e.g. a consortium).
“Concerning 1: Equity from the latest annual report must be at least DKK 10 000 000 or EUR 1 350 000.
Concerning 2: Equity ratio from the latest annual...”
Concerning 1: Equity from the latest annual report must be at least DKK 10 000 000 or EUR 1 350 000.
Concerning 2: Equity ratio from the latest annual report must be at least 20 pct. If the equity ratio is between 15 pct. and 20 pct. the applicant can qualify, if Equity exceeds the total expected amount of the contract (total expected among of one lot).
Vis mere Teknisk og faglig kompetence
Liste og kortfattet beskrivelse af udvælgelseskriterier:
“The applicant must include the up to 6 most comparable and relevant references in total for both lots undertaken in the past five 5 years as part of the...”
Liste og kortfattet beskrivelse af udvælgelseskriterier
The applicant must include the up to 6 most comparable and relevant references in total for both lots undertaken in the past five 5 years as part of the application. The references must be stated in the ESPD part IV.C: ‘Technical and professional ability’. Undertaken in the past five (5) years implies that the reference must not have been completed prior to the date reached when counting 5 years backwards from the submission date for pre-qualification. References older than this will not be taken into consideration. References which have not yet been fully completed can be included as part of the application, but if this is the case, the applicant must describe the parts which have not yet been delivered, and this may affect the evaluation of the applicant, cf. section II.2.9).
The references should include:
• a specific description of the work performed for each reference, including:
— a project description;
— a description of the services delivered with focus on topics relevant to tendered assignment under Energy Is-lands and Offshore wind farms in the North Sea and the Baltic Sea;
• contract value (if possible);
• contact information for the entity in question (including contact person);
• date of initiation and final delivery (day, month, year).
Applicants are encouraged to limit each reference to a maximum of one page.
Any ambiguities and/or incomprehensibilities concerning the above information may have a negative effect on the selection of candidates, cf. section II.2.9). Please note the ‘description’ box can contain more text than is visible. I.e. it is possible to copy paste text into the box.
If the applicant is relying on the references of one or more other entities (e.g. a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the information for the ESPD part IV.C must also be given in a separate ESPD from each of these entities.
The number of references should not surpass a maximum of the 6 most comparable and relevant references in total for both lots. If the applicant is relying on the capacity of one or more other entities (e.g. a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the maximum number of references to be submitted must still be respected and cannot exceed 6 when combined. If more than 6 references are submitted, the contracting authority will only consider the 6 most recent references determined by date of final delivery (in this case not yet finished references will not be included).
Vis mere Betingelser for deltagelse
Betingelser for deltagelse (tekniske og faglige kvalifikationer):
“The applicant must document:
• two (2) references regarding environmental assessment (SEA and/or EIA) of an offshore infrastructure project;
• two (2)...”
Betingelser for deltagelse (tekniske og faglige kvalifikationer)
The applicant must document:
• two (2) references regarding environmental assessment (SEA and/or EIA) of an offshore infrastructure project;
• two (2) references regarding environmental assessment (SEA and/or EIA) of an onshore infrastructure project;
• one (1) reference regarding studies and impact assessment on marine mammals;
• one (1) reference regarding studies and impact assessment on birds.
The same reference may cover more than one of the provisions listed above.
The applicant must have implemented and maintain a quality management system in compliance with ISO 9001 (or equivalent).
The applicant must have implemented and maintain a health, safety and environment management system. This management system shall comply with the latest edition of OHSAS 18001, ISO 45001, DNV OS-H101, ISO 14001 or other equivalent international standards as applicable.
Vis mere
Liste og kortfattet beskrivelse af regler og kriterier:
“The applicant must submit a completed version of the ESPD.
Applicants may not be subject to the mandatory grounds for exclusion, cf. the Danish Public...”
Liste og kortfattet beskrivelse af regler og kriterier
The applicant must submit a completed version of the ESPD.
Applicants may not be subject to the mandatory grounds for exclusion, cf. the Danish Public Procurement Act (udbud-sloven) Section 135 (1-3) and 136.
Please see section VI.3) ‘Additional information’ for further information regarding the ESPD. The application must be submitted through EU-Supply, cf. link in section I.1) in this notification. Applications not submitted via EU-supply or received after the deadline will not be accepted.
The contracting authority reserves the right to request the applicant to supplement, specify or complete the information submitted.
Vis mere
Krav om deponering og sikkerhedsstillelse: The information is stated in the tender documents.
De vigtigste finansieringsbetingelser og betalingsordninger og/eller henvisning til de relevante bestemmelser, der regulerer dem: The information is stated in the tender documents.
Den juridiske form, som den sammenslutning af økonomiske aktører, der skal have kontrakten, skal have:
“No special legal form is required.
If the agreements are awarded to a group of economic operators (e.g. a consortium) the participants are required to...”
Den juridiske form, som den sammenslutning af økonomiske aktører, der skal have kontrakten, skal have
No special legal form is required.
If the agreements are awarded to a group of economic operators (e.g. a consortium) the participants are required to undertake joint and several liabilities and to appoint one economic operator to represent the group.
Vis mere Betingelser i forbindelse med kontrakten
Betingelser for opfyldelse af kontrakten: The information is stated in the tender documents.
Procedure Type af procedure
Forhandlet procedure med forudgående indkaldelse af konkurrencer
Oplysninger om reduktion af antallet af løsninger eller tilbud under forhandling eller dialog
Anvendelse af en trinvis procedure for gradvist at reducere antallet af løsninger, der skal drøftes, eller af tilbud, der skal forhandles
Administrative oplysninger
Frist for modtagelse af bud eller ansøgninger om deltagelse: 2021-03-23
10:00 📅
Sprog, på hvilke bud eller ansøgninger om deltagelse kan indgives: engelsk 🗣️
Nedenstående tidsramme er udtrykt i antal måneder.
Minimumsfrist, inden for hvilken tilbudsgiveren skal opretholde tilbuddet: 3
Supplerende oplysninger Oplysninger om elektroniske arbejdsgange
Elektronisk fakturering vil blive accepteret
Der vil blive anvendt elektronisk betaling
Yderligere oplysninger
“The applicant must submit a completed ESPD to apply for pre-qualification for this tender procedure. The ESPD for this tender can be found via EU-supply....”
The applicant must submit a completed ESPD to apply for pre-qualification for this tender procedure. The ESPD for this tender can be found via EU-supply. The ESPD must be completed in EU-Supply and submitted via ‘My Response’.
Please note:
— An applicant participating on its own, but relying on the capacities of one or more other entities (e.g. a parent or sister company or a subcontractor), must ensure that the application includes the applicants own ESPD together with a separate ESPD from each of the entities it relies on with a completed part II: ‘Information concerning the economic operator’ and part III: ‘Exclusion grounds’ of the ESPD as well as the relevant information regarding part IV: ‘Selection criteria’ and part V: ‘Reduction of the number of qualified candidates’. The ESPD from each of the entities should be duly filled and signed by the entities concerned.
Further where an applicant wants to rely on the capacities of other entities, it shall prove to the contracting authority that it will have at its disposal the resources necessary, for example, by producing a commitment by those entities to that effect, which must be submitted as part of the final documentation.
— Where groups of economic operators, including temporary associations, participate together in the procurement procedure, a complete separate ESPD for each of the participating economic operators must be submitted.
Further the final documentation must include a signed declaration by all parties of the group of economic operators (joint venture, consortium or other) stating that all economic operators as-sume joint and several liabilities towards the contracting authority for the performance of the contract as a whole.
Vis mere Gennemgå organ
Navn: Klagenævntet for Udbud
Postadresse: Nævnenes Hus, Toldboden 2
Postby: Viborg
Postnummer: 8800
Land: Danmark 🇩🇰
Telefon: +45 72405708📞
E-mail: klfu@naevneneshus.dk📧
URL: https://naevneneshus.dk/start-din-klage/klagenaevnet-for-udbud/🌏 Gennemgangsprocedure
Præcise oplysninger om fristerne for gennemgangsprocedurer:
“Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the...”
Præcise oplysninger om fristerne for gennemgangsprocedurer
Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision.
Other complaints must be filed with The Complaints Board for Public Procurement within:
1) 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date);
2) 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision;
3) 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Vis mere Tjeneste, hvorfra der kan indhentes oplysninger om klageproceduren
Navn: Konkurrence- og Forbrugerstyrelsen
Postadresse: Carl Jacobsen Vej 35
Postby: Valby
Postnummer: 2500
Land: Danmark 🇩🇰
Telefon: +45 41715000📞
E-mail: kfst@kfst.dk📧
URL: http://www.kfst.dk🌏
Kilde: OJS 2021/S 046-116639 (2021-03-03)
Bekendtgørelse om indgåede kontrakter (2021-09-27) Objekt Omfanget af udbuddet
Titel:
“Strategic environmental assessment (SEA) and environmental investigations for Offshore wind farms and energy islands in the North Sea and the Baltic Sea
21/01698”
Titel
Strategic environmental assessment (SEA) and environmental investigations for Offshore wind farms and energy islands in the North Sea and the Baltic Sea
21/01698
Vis mere
Kort beskrivelse:
“With the Climate Agreement for Energy and Industry of the 22nd of June 2020 the majority of the Dan-ish Parliament decided that Denmark will become the...”
Kort beskrivelse
With the Climate Agreement for Energy and Industry of the 22nd of June 2020 the majority of the Dan-ish Parliament decided that Denmark will become the first country in the world to begin the construc-tion of two energy island with a total capacity of 5 GW offshore wind.
One of the islands will be located in the North Sea with a capacity of 3 GW. This island can be further scaled up to 10 GW offshore wind. The other energy island will be established on the current island of Bornholm with a capacity of 2 GW. The islands are scheduled for completion by 2030.
Following the political decision, the Danish Energy Agency has instructed the Energinet to initiate site investigations, environmental and metocean studies and analysis for grid connection for the area of investigation.
Vis mere
Samlet værdi af indkøbsaftalen (ekskl. moms): EUR 2 983 005 💰
Oplysninger om partier
Denne kontrakt er opdelt i partier ✅ Omfanget af udbuddet
Titel:
“Strategic environmental assessment (SEA) and environmental investigations for Offshore wind farms and energy islands in the North Sea” Beskrivelse
Hovedsted eller sted for udførelsen:
“The North Sea The investigation area – which is located approximately 100 km west of Harboøre (Jutland) – and at Energinets and Consultants offices”
Beskrivelse af udbuddet:
“A broad coalition of Danish parties decided on June 22, 2020 to initiate the realization of two energy islands:
In the North Sea, as an artificial island,...”
Beskrivelse af udbuddet
A broad coalition of Danish parties decided on June 22, 2020 to initiate the realization of two energy islands:
In the North Sea, as an artificial island, which will serve as a hub for offshore wind farms with a total capacity of 3 GW and potentially up to 10 GW in the future.
In the Baltic Sea, the Island of Bornholm will be the physical hub for offshore wind farms with a total capacity of 2 GW.
Both energy islands will export power to the mainland of Denmark and neighboring countries and are intended to serve as a hub that collects electricity from the surrounding offshore windfarms and distributes the electricity between countries via electricity grid connections.
One of the islands will be located in the North Sea with a capacity of 3 GW, and this island will be extended in stages as the construction of new international connections to neighboring countries are developed, and the demand of power will increase. In the future, the island can be further scaled up to 10 GW offshore wind. The other energy island will be established on the current island of Bornholm with a capacity of 2 GW.
Following the political decision, the Danish Energy Agency has instructed the Energinet to initiate site investigations, environmental and metocean studies and analysis for grid connection for the area of investigation. The current tender (lot 1) concerns consultancy services for preparing environmental assessments, planning consents and marine environmental baseline investigations for an energy island with surrounding offshore wind farms in the North Sea.
The current tender concerns consultancy services for preparing environmental assessments, planning consents and marine environmental baseline investigations for two energy islands and offshore wind projects in Denmark.
For further details concerning the purchase, reference is made to the Scope of Services.
The tendered assignment is divided into 2 lots. Lot 1 concerns the North Sea and lot 2 concerns the Baltic Sea. Tenderers applying for prequalification will apply for both lot 1 and lot 2. Regardless of the Tenderers being prequalified for lot 1 and lot 2, a Tenderer will maximum be awarded one (1) lot. Lot 1 will be prioritized, and the Tenderer awarded lot 1 will therefore have its tender-offer for lot 2 taken out of the evaluation for lot 2.
For further details concerning the purchase, reference is made to the Scope of Services and the rest of the tender material.
Vis mere
Yderligere oplysninger:
“Please note that this is a negotiated procedure. With the exception of mandatory parts, the Tender Documents may as a result undergo changes as part of the...”
Yderligere oplysninger
Please note that this is a negotiated procedure. With the exception of mandatory parts, the Tender Documents may as a result undergo changes as part of the negotiation process.
Vis mere Omfanget af udbuddet
Titel:
“Strategic environmental assessment (SEA) and environmental investigations for Offshore wind farms and energy islands in the Baltic Sea” Beskrivelse
Hovedsted eller sted for udførelsen:
“The Baltic Sea The investigation area – which is located approximately 20 km south/west of Bornholm (The Baltic Sea) – and at Energinets and Consultants offices”
Hovedsted eller sted for udførelsen
The Baltic Sea The investigation area – which is located approximately 20 km south/west of Bornholm (The Baltic Sea) – and at Energinets and Consultants offices
Vis mere
Beskrivelse af udbuddet:
“A broad coalition of Danish parties decided on June 22, 2020 to initiate the realization of two energy islands:
In the North Sea, as an artificial island,...”
Beskrivelse af udbuddet
A broad coalition of Danish parties decided on June 22, 2020 to initiate the realization of two energy islands:
In the North Sea, as an artificial island, which will serve as a hub for offshore wind farms with a total capacity of 3 GW and potentially up to 10 GW in the future.
In the Baltic Sea, the Island of Bornholm will be the physical hub for offshore wind farms with a total capacity of 2 GW.
Both energy islands will export power to the mainland of Denmark and neighboring countries and are intended to serve as a hub that collects electricity from the surrounding offshore windfarms and distributes the electricity between countries via electricity grid connections.
One of the islands will be located in the North Sea with a capacity of 3 GW, and this island will be extended in stages as the construction of new international connections to neighboring countries are developed, and the demand of power will increase. In the future, the island can be further scaled up to 10 GW offshore wind. The other energy island will be established on the current island of Bornholm with a capacity of 2 GW.
Following the political decision, the Danish Energy Agency has instructed the Energinet to initiate site investigations, environmental and metocean studies and analysis for grid connection for the area of investigation. The current tender (lot 2) concerns consultancy services for preparing environmental assessments, planning consents and marine envi-ronmental baseline investigations for an energy island with surrounding offshore wind farms in the Baltic Sea.
The current tender concerns consultancy services for preparing environmental assessments, planning consents and marine environmental baseline investigations for two energy islands and offshore wind projects in Denmark.
For further details concerning the purchase, reference is made to the Scope of Services.
The tendered assignment is divided into 2 lots. Lot 1 concerns the North Sea and lot 2 concerns the Baltic Sea. Tenderers applying for prequalification will apply for both lot 1 and lot 2. Regardless of the Tenderers being prequalified for lot 1 and lot 2, a Tenderer will maximum be awarded one (1) lot. Lot 1 will be prioritized, and the Tenderer awarded lot 1 will therefore have its tender-offer for lot 2 taken out of the evaluation for lot 2.
For further details concerning the purchase, reference is made to the Scope of Services and the rest of the tender material.
Procedure Administrative oplysninger
Tidligere offentliggørelse vedrørende denne procedure: 2021/S 046-116639
Tildeling af kontrakt
1️⃣
Kontraktnummer: 1
Titel: Lot 1
Dato for indgåelse af kontrakten: 2021-09-23 📅
Navn og adresse på kontrahenten
Navn: Niras
Nationalt registreringsnummer: 37295728
Postadresse: Sortemosevej 19
Postby: Allerød
Postnummer: 3450
Land: Danmark 🇩🇰
E-mail: hhl@niras.dk📧
Region: Danmark🏙️
Entreprenøren er en SMV
Oplysninger om kontraktens/parcellens værdi (ekskl. moms)
Kontraktens/parcellens samlede værdi: EUR 1 477 915 💰
2️⃣
Kontraktnummer: 2
Titel: Lot 2
Dato for indgåelse af kontrakten: 2021-09-14 📅
Navn og adresse på kontrahenten
Navn: Ramboll Denmark - Water / Environment & Health
Nationalt registreringsnummer: 35128417
Postadresse: Hannemanns Allé 53
Postby: Copenhagen S
Postnummer: 2300
Telefon: +45 51616041📞
E-mail: ger@ramboll.dk📧 Oplysninger om kontraktens/parcellens værdi (ekskl. moms)
Kontraktens/parcellens samlede værdi: EUR 1 505 090 💰
Supplerende oplysninger Yderligere oplysninger
“The applicant must submit a completed ESPD to apply for prequalification for this tender procedure. The ESPD for this tender can be found via EU-supply. The...”
The applicant must submit a completed ESPD to apply for prequalification for this tender procedure. The ESPD for this tender can be found via EU-supply. The ESPD must be completed in EU-Supply and submitted via “My Response”.
Please note:
- An applicant participating on its own, but relying on the capacities of one or more other entities (e.g. a parent or sister company or a subcontractor), must ensure that the application includes the applicants own ESPD together with a separate ESPD from each of the entities it relies on with a completed part II: “Information concerning the economic operator” and part III: “Exclusion grounds” of the ESPD as well as the relevant information regarding part IV: “Selection criteria” and part V: “Reduction of the number of qualified candidates”. The ESPD from each of the entities should be duly filled and signed by the entities concerned.
Further where an applicant wants to rely on the capacities of other entities, it shall prove to the contracting authority that it will have at its disposal the resources necessary, for example, by producing a commitment by those entities to that effect, which must be submitted as part of the final documentation.
- Where groups of economic operators, including temporary associations, participate together in the procurement procedure, a complete separate ESPD for each of the participating economic operators must be submitted.
Further the final documentation must include a signed declaration by all parties of the group of economic operators (joint venture, consortium or other) stating that all economic operators as-sume joint and several liabilities towards the Contracting Authority for the performance of the contract as a whole.