Kriegers Flak Combined Grid Solution Burial and Protection of 150 kV Submarine Cables
Kriegers Flak CGS (Combined Grid Solution) is a joint project between Energinet.dk and 50Hertz Transmission to interconnect the Danish and German grid via the two offshore wind farms at Krieger's Flak (DK) and Baltic 2 (DE). The Contracting Entity wants to procure Burial and Protection of approximately 2 x 24 km of submarine cable route, which is to be divided into trenching and jetting work for the Krieger's Flak CGS connection. The works includes inter alia:
1. Boulder Removal
2. Pre-trenching/trenching
3. Jetting
4. Covering the Trench
5. Surveys and Documentation.
Deadline
Fristen for modtagelse af bud var på 2016-12-29.
Indkøbet blev offentliggjort på 2016-12-08.
Hvem?
Hvad?
Hvor?
Indkøbshistorik
Dato |
Dokument |
2016-12-08
|
Udbudsbekendtgørelse
|
2017-10-03
|
Bekendtgørelse om indgåede kontrakter
|