Replacement of well head and production piping in natural gas caverne

Energinet.dk

Consulting and engineering related to replacing well head and production string in natural gas caverne To-6. Certified well engineering and supervision. Tasks include among other preparation of: Specification of activities and materials for purchase. Working program, Rock Mechanical Assessment and other documents for authority approval.
The gas storage consist of 7 almost identical cavernes. Further to the one to be quoted, prices for additional 4 cavernes are requested. These can be ordered one by one.

Deadline
Fristen for modtagelse af bud var på 2015-02-24. Indkøbet blev offentliggjort på 2015-02-09.

Hvem?

Hvad?

Hvor?

Indkøbshistorik
Dato Dokument
2015-02-09 Udbudsbekendtgørelse