Hangar Project 2015 — Thetis Class
The Danish Defence has acquired new Seahawk Helicopter and therefore the 4 vessels of the Thetis class needs modifications to accommodate these helicopters as well as new RHIBs (Rigid-Hulled Inflatable Boat) for the Navy. The contract will comprise two of the vessels (Vædderen and Hvidbjørnen) and 2 further vessels (Thetis and Triton) will be optional.
The services will have to be performed within the following periods: The works on Vædderen are expected to be performed from 27.7.2015 and approximately the following 21 weeks. The works are to be performed on Hvidbjørnen from the beginning of 2016 and a total of 21 weeks. As for the optional vessels the periods are expected for Thetis October 2016 until March 2017 and Triton October 2017 until March 2018.
The supplier shall accept other works to be carried out by DALO or other suppliers during the vessels stay at the Suppliers premises for the works performed under this tender procedure. This will for instance be the case on the installation of Davit Launch Systems and Landinglights.
The vessels are based at the Naval Base Frederikshavn. The cost of sailing to another place, the cost of guarding the ship while there, and extra cost in respect of the personnel of The Danish Defence that will need to travel to the place the vessel is deployed to will be be added when evaluating the prices offered. This is done solely for the purpose of evaluation, and the winning tenderer will not have to cover these costs.
The refiting will primarily concern the hangar area, landingdeck and sidedecks. Furthermore new rooms/areas has to be established and necessary follow-up works.
The services will among others contain:
— Dismantling of the existing hangar;
— Enhancement of the stern, including beneath the helicopter deck and hangar area;
— Establishing of the new hangar appropriate for the Seahawk Helicopters, including;
— re-installation of material, equipment and functionalities;
— establishing of new functionalities; and
— re-installation of the stern mast;
— Establishment of water-mist
— Establishing of to closed area for vessels with folded gates on the outside of the new hangar;
— Establishing the foundation for the Davit Launch Systems;
— Adapting of the helicopter deck, including;
— moving of the existing landing grid and other adaptions of existing functionalities;
— adapting of landing lights (not delivery of these) and other lights on the deck and change of existing coating of the deck, including painting/marking of helicopter deck;
— establishing of service-cranes on the helicopter deck;
— Establishing of storage rooms under the hangar;
— Establishing of workshops and rooms for equipment in the stern and superstructure;
— Adapting of foundations for new materials on the bridge, rooms for equipment etc.;
— Adapting of cables and pipes in connection with the works.
Deadline
Fristen for modtagelse af bud var på 2015-03-03.
Indkøbet blev offentliggjort på 2015-01-30.
Leverandører
Følgende leverandører er nævnt i tildelingsbeslutninger eller andre indkøbsdokumenter:
Hvem?
Hvad?
Indkøbshistorik
Dato |
Dokument |
2015-01-30
|
Udbudsbekendtgørelse
|
2015-06-30
|
Bekendtgørelse om indgåede kontrakter
|