Supply and installation of conveyors

Afatek A/S

Afatek A/S is owned by five public waste management companies, covering the eastern part of Denmark. From its owners, Afatek receive Incinerator Bottom Ash (IBA) which is transported to Afatek's 3 sites for treatment and storage. Afterwards, the bottom ash gravel is used in the construction of roads. Afatek focusses on recovery of ferrous and non-ferrous metals from the IBA. This is partially in order to recover as much metal as possible, but also for the purpose of obtaining a high quality bottom ash gravel for road construction.
It is AFATEK's intention to construct a high speed metal sorting plant on site (Selinevej 18 DK-2300 Copenhagen S). It is intended to be one of the internationally most advanced plants as the plant shall recover ferrous and non-ferrous metals down to grain size 0,5 mm based on wet discharged IBA being dried up by use of natural ageing. Also stainless steel will be recovered. The metal sorting plant is to be established based on three separate lots/contracts (three different calls for tenders), one regarding the screens, one regarding the conveyor belts and one regarding the sorting machines.
This call for tenders regards the award of a contract for supply and installation of conveyor belts which will form part of the metal sorting plant.
Scope of supply:
1. Design of and supply of conveyor belts and feeding system, incl. steel structures.
2. Supply of windsifters.
3. Transportation of conveyor belts, feeding system, steel structures, wind sifters to Afatek site in Copenhagen.
4. Installation of conveyor belts, feeding system, steel structures, wind sifters.
5. Detailed project, installation, commissioning, performance test.
6. Project management for the complete project, including detailed engineering and coordination with suppliers of screens and sorting machines (option).
The supplier of conveyors shall deliver complete units of conveyors with steel structures, carry out a detailed project including a mounting plan, deliver the equipment on the site in Copenhagen, carry out the mounting work and participate in test run of the plant. During the detailed projection of the conveyor supply and the total plant, adjustments of the conveyor supply takes place, i.e. height of the steel structures and length of conveyors.
Afatek may choose (as an option) that the conveyor supplier shall also carry out coordination of the detailed projection of the entire/total plant (the coordination/project management between the three different suppliers/contracts), installation on the site, test run and the process of commissioning of the plant.
The budget for the contract (incl. options) is approx. EUR 2 000 000.
Further information is made available in the tender documents at http://database.afatek.dk/Login/udbud/udbud.html under ‘Supply of Conveyors for the Afatek Metal Sorting Plant’.
Coordination with other suppliers:
As the supply is part of a metal sorting plant consisting of also screens and sorting machines, attention shall be given to the tender material of these supplies (Supply of Screens and Supply of Sorting Machines) that can also be found on the webpage mentioned above.

Deadline
Fristen for modtagelse af bud var på 2015-02-09. Indkøbet blev offentliggjort på 2014-12-15.

Leverandører
Følgende leverandører er nævnt i tildelingsbeslutninger eller andre indkøbsdokumenter:
Hvem?

Hvad?

Indkøbshistorik
Dato Dokument
2014-12-15 Udbudsbekendtgørelse
2015-05-07 Bekendtgørelse om indgåede kontrakter