Biomass fired combined heat and power plant in Lisbjerg, S01 Distributed Control System and Video Surveillance System
The Purchase includes a Distributed Control System (DCS) and Video Surveillance System (VSS) for a straw fired combined heat and power plant.
The straw fired combined heat and power plant shall be monitored and controlled from a central control room placed in an existing waste-to-energy Plant, which is placed nearby the new plant.
The operation of the new DCS and VSS shall therefore be integrated in the central control room. The DCS and VSS must also be able to be operated from a control room placed in the new plant.
The purchase including:
— Delivery and installation of a DCS including hardware and programming
— Delivery and programming of approx. 2 500-3 000 remote I/O equipment for the DCS.
— Programming of approx. 3 000 signals for bus-based signal exchange between DCS and auxiliary equipment.
— Programming will be based on functional description from the process contractors.
— Design, programming, test and commissioning of coordinating control.
— Delivery and installation of optical fibre cables between the DCS and remote I/O equipment placed in the process area.
— Delivery and installation of a complete Video Surveillance System. Approx. 30-40 cameras.
— Testing and commissioning in co-operation with the Employer.
Deadline
Fristen for modtagelse af bud var på 2014-09-26.
Indkøbet blev offentliggjort på 2014-08-28.
Leverandører
Følgende leverandører er nævnt i tildelingsbeslutninger eller andre indkøbsdokumenter:
Hvem?
Hvad?
Hvor?
Indkøbshistorik
Dato |
Dokument |
2014-08-28
|
Udbudsbekendtgørelse
|
2015-07-16
|
Bekendtgørelse om indgåede kontrakter
|