DTU Life Science and Bioengineering — Contract E202-02 - Execution of structural concrete and structual steel works
The construction contract concerns the construction of a carcass (structual) for a new three storey research and laboratory building with two storey basement. The size of the building is approx. 27 000 m².
In outline, the work consists of:
a) establishing safety measures and keeping excavation pit dry,
b) fine grade excavation,
c) casting app. 2 100 m³ in situ foundation on intact sand bedding,
d) underground Waste Water and drainage system,
e) app. 3 000 m² in situ cast concrete basement walls,
f) delivery and mounting of app. 15 000 m² element walls,
g) Supply and mounting of app. 21 000 m² hollow core precast concrete slabs and filigree slabs including app. 2 000 m composite steel beams,
h) delivery and mounting of steel lattice girders and trusses in roof,
i) pouring of self leveling screed on concrete slabs,
j) close-off of roof, including roof building and provisional draining off of rain water,
k) permanent weather-proof facade closing of roof buildingexcl. final facade cladding,
l) provisional weather-proof facade closing of main building.
Deadline
Fristen for modtagelse af bud var på 2013-12-20.
Indkøbet blev offentliggjort på 2013-11-19.
Leverandører
Følgende leverandører er nævnt i tildelingsbeslutninger eller andre indkøbsdokumenter:
Hvem?
Hvad?
Hvor?
Indkøbshistorik
Dato |
Dokument |
2013-11-19
|
Udbudsbekendtgørelse
|
2015-03-25
|
Bekendtgørelse om indgåede kontrakter
|