Frøslev-Egtved II, Gas Pipeline, Pipeline Construction

Energinet.dk

The contract comprise the construction of a DN 750 (30 inch), approx. 94 km high pressure (80 bar) steel gas transmission pipeline parallel to the existing DN 600 gas transmission pipeline from the Danish/German border at Frøslev to compressor station at Egtved, Jutland, Denmark. The contract will comprise construction of 3 valve stations along the pipeline, and scraper facilities either end of the pipeline. The construction works shall be based on a detailed design tender package provided by the Employer.
All line pipes, fittings, valves, scraper traps, etc. will be supplied by the Employer as free issue materials.
The pipeline shall be constructed in material EN 10208-2 L485MB.
The pipeline is primarily passing through agricultural districts. There are approximately 35 water crossings, 75 road crossings, 1 railway crossing and approximately 7 Nos. of totally 2 300 m of horizontal directional drillings along the pipeline route.

Deadline
Fristen for modtagelse af bud var på 2011-05-17. Indkøbet blev offentliggjort på 2011-03-22.

Hvem?

Hvad?

Hvor?

Indkøbshistorik
Dato Dokument
2011-03-22 Udbudsbekendtgørelse