Billund Lufthavn, EDS 2012 (explosive detection systems)

Billund Lufthavn A/S

Billund Lufthavn (airport) must change the existing EDS units in the baggage handling system in order to meet the EU standard 2 regulations. For this purpose 2 or 3 new EDS units (explosive detection systems) shall be built in the baggage handling system in the existing passenger terminal building. The 2 or 3 new EDS units shall be in operation by June 2012.
The scope of work comprises of authorities approval, delivery, dismantling of existing EDS units, erection and commissioning of the 2 or 3 new EDS units. Each of the EDS units must be able to screen minimum 1 500 pieces of baggage per hour.

Deadline
Fristen for modtagelse af bud var på 2011-08-29. Indkøbet blev offentliggjort på 2011-07-07.

Hvem?

Hvad?

Hvor?

Indkøbshistorik
Dato Dokument
2011-07-07 Udbudsbekendtgørelse
2012-08-27 Bekendtgørelse om indgåede kontrakter