De seneste indkøb foretaget af Viborg Fjernvarme m.fl.
2011-12-12Casing for geothermal project (Viborg Fjernvarme m.fl.)
This scope of work is to supply the operator with casing for a geothermal project for up to 20 optional wells at 4 different locations in Jutland, Denmark. If flow tests are positive the optional wells are expected. The tender is on behalf of Viborg Fjernvarme, Skive Geotermi A/S, Tønder Fjernvarme A.m.b.a. og Aabenraa-Rødekro Fjernvarme A.m.b.a.
Se udbuddet »
2011-08-08Cuttings handling and garbage disposal (Viborg Fjernvarme m.fl.)
Prækvalifikation for service vedrørende håndtering af borespåner i forbindelse med geotermiske boringer i Jylland. Der er udbudt op til 22 mulige boringer, men udfald af prøveboring og prøvepumpning er afgørende for, om alle boringer udføres. Udbuddet sker på vegne af 4 myndigheder: Viborg Fjernvarme, Tønder Fjernvarme, Aabenraa-Rødekro Fjernvarme og Skive Kommunes kommende geotermis selskab Skive Geotermi A/S under stiftelse.
Arbejdet består i håndtering af borespåner intern på boreplads, ansvar for …
Se udbuddet »
2011-07-08Cuttings handling and garbage disposal (Viborg Fjernvarme m.fl.)
Prækvalifikation for service vedrørende håndtering af borespåner i forbindelse med geotermiske boringer i Jylland. Der er udbudt op til 22 mulige boringer, men udfald af prøveboring og prøvepumpning er afgørende for, om alle boringer udføres. Udbuddet sker på vegne af 4 myndigheder: Viborg Fjernvarme, Tønder Fjernvarme, Aabenraa-Rødekro Fjernvarme og Skive Kommunes kommende geotermis selskab Skive Geotermi A/S under stiftelse.
Arbejdet består i håndtering af borespåner intern på boreplads, ansvar for …
Se udbuddet »
2011-07-04Line hanger, sand screens and well heads (Viborg Fjernvarme m.fl.)
Prequalification for line hanger, sand screens and well heads for 4 geothermal exploration wells and 22 optional wells at 4 different locations in Jutland, Denmark. If the result of the flow test in the 4 exploration wells is positive, up to 22 optional wells are expected. The contractor is to supply the operator with line hanger, sand screen and well heads service that will be required to drill, test and complete wells to a depth between 2 500 to 3 500 m. (vertical, deviated or horizontal). The …
Se udbuddet »
2011-06-30Wireline Logging (Viborg Fjernvarme m.fl.)
Prequalification for Wireline Logging service for 4 geothermal exploration wells and 22 optional wells at 4 different locations in Jutland, Denmark. If the result of the flow test in the 4 exploration wells is positive, up to 22 optional wells are expected. The scope of work for the service is to supply the operator with wireline logging service that will be required to drill, test and complete wells to a depth between 2 500 to 3 500 m. (vertical, deviated or horizontal). The programme is to drill a 17 …
Se udbuddet »
2011-06-30Mud Logging (Viborg Fjernvarme m.fl.)
Prequalification for provisions of mud logging service for 4 geothermal exploration wells and 22 optional wells at 4 different locations in Jutland, Denmark. If the result of the flow test in the 4 exploration wells is positive, up to 22 optional wells are expected. The scope of work for the service is to supply the operator with mud logging service in connection with drill, test and completion of wells to a depth between 2500 to 3500 m. (vertical, deviated or horizontal). The programme is to drill a 17 …
Se udbuddet »
2011-06-29Directional Drilling and MWD (Viborg Fjernvarme m.fl.)
Prequalification for provisions of directional drilling and MWD for 4 geothermal exploration wells and 22 optional wells at 4 different locations in Jutland, Denmark. If the result of the flow test in the 4 exploration wells is positive, up to 22 optional wells are expected. The scope of work for service is to supply the operator with directional drilling and MWD that will be required to drill, test and complete wells to a depth between 2500 to 3500 m. (vertical, deviated or horizontal). The programme is …
Se udbuddet »
2011-06-28Drilling Fluid Materials (Viborg Fjernvarme m.fl.)
Prequalification for Drilling Fluids Materials for 4 geothermal exploration wells and 22 optional wells at 4 different locations in Jutland, Denmark. If the result of the flow test in the 4 exploration wells is positive, up to 22 optional wells are expected. The contractor is to supply the operator with Drilling Fluids Materials that will be required to drill, test and complete wells to a depth between 2500 to 3500 m. (vertical, deviated or horizontal). The programme is to drill a 17 ½” hole, set a 13 ⅜” …
Se udbuddet »
2011-06-27Cementing service (Viborg Fjernvarme m.fl.)
Prequalification for cementing service for 4 geothermal exploration wells and 22 optional wells at 4 different locations in Jutland, Denmark. If the result of the flow test in the 4 exploration wells is positive, up to 22 optional wells are expected. The contractor is to supply the operator with cementing service that will be required to drill, test and complete wells to a depth between 2500 to 3500 m. (vertical, deviated or horizontal). The programme is to drill a 17 ½” hole, set a 13 ⅜” casing at +/- …
Se udbuddet »
2011-06-22Drilling bits (Viborg Fjernvarme m.fl.)
Prequalification for provisions of drilling bits service for 4 geothermal exploration wells and 22 optional wells at 4 different locations in Jutland, Denmark. If the result of the flow test in the 4 exploration wells is positive, up to 22 optional wells are expected. The scope of work for the applicant is to supply the operator with drilling bits service of various types (PDC and Tricone) that will be required to drill, test and complete wells to a depth between 2 500 to 3 500 m. (vertical, deviated or …
Se udbuddet »
2011-05-19Land drilling rig for geothermal wells (Viborg Fjernvarme m.fl.)
Tender for a land drilling rig for geothermal wells. The tender is on behalf of 4 different contracting authorities - Viborg Fjernvarme, Skive Kommune, Tønder Fjernvarme og Aabenraa Fjernvarme - who each has separate projects. Drilling locations will be at 4 different places in Jutland, Denmark.
There will be 4 firm exploration wells at 4 different locations and - depending on the outcome of a flow tests - approximately 22 optional wells.
The first exploration well is expected to begin mid August 2011 …